RERA’d by NeevHQ

Projects · MAX ESTATES GURGAON TWO LIMITED

Estate 361

Max Estates Gurgaon Two · Sector 36, Gurugram

Registered with RERA: Nov 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 36; the exact site was not found.

The builder: Max Estates Gurgaon Two

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameESTATE 361
Builder (promoter)MAX ESTATES GURGAON TWO LIMITED
LocationVILLAGE-HARSARU, SECTOR 36
RERA project IDRERA-GRG-2093-2025
Registration certificate numberGGM/1012/744/2025/115 DATED 21.11.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/09/2033
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area14.2944 acres
Licence50 of 2025 valid up to 08.04.2030
Estimated cost of the project₹5,86,185 lakh (₹5,861.85 crore)
Total units (plots, apartments, shops)1352
Unit sizes (carpet area, as declared)1 unit of 176 sq ft carpet (1 tower); 1 unit of 195 sq ft carpet (1 tower); 236 units of 200 sq ft carpet (1 tower); 1 unit of 222 sq ft carpet (1 tower); 1 unit of 261 sq ft carpet (1 tower); 1 unit of 338 sq ft carpet (1 tower); 1 unit of 357 sq ft carpet (1 tower); 1 unit of 417 sq ft carpet (1 tower); 1 unit of 418 sq ft carpet (1 tower); 1 unit of 445 sq ft carpet (1 tower); 1 unit of 457 sq ft carpet (1 tower); 1 unit of 522 sq ft carpet (1 tower); 1 unit of 544 sq ft carpet (1 tower); 1 unit of 551 sq ft carpet (1 tower); 1 unit of 569 sq ft carpet (1 tower); 1 unit of 594 sq ft carpet (1 tower); 124 units of 595 sq ft carpet (1 tower); 105 units of 798 sq ft carpet (1 tower); 134 units of 814 sq ft carpet (1 tower); 17 units of 877 sq ft carpet (1 tower); 88 units of 1,250 sq ft carpet (2 towers); 8 units of 1,449 sq ft carpet (2 towers); 132 units of 1,464 sq ft carpet (2 towers); 8 units of 1,514 sq ft carpet (2 towers); 256 units of 1,742 sq ft carpet (2 towers); 124 units of 1,863 sq ft carpet (2 towers); 88 units of 2,196 sq ft carpet (2 towers); 2 units of 2,844 sq ft carpet (1 tower); 2 units of 3,199 sq ft carpet (1 tower); 2 units of 3,269 sq ft carpet (2 towers); 4 units of 3,389 sq ft carpet (2 towers); 2 units of 4,054 sq ft carpet (2 towers); 1 unit of 5,249 sq ft carpet (1 tower); 1 unit of 6,752 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on16-10-2025
Building plans approved on16-10-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction05-03-2026
Likely completion date30-09-2033

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on13-Oct-2026
Quarterly reports listed on the portal3

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹12,060.5 lakh (₹120.61 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,576.48 lakh (₹15.76 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹5,936.87 lakh (₹59.37 crore)
Project bank account (escrow): deposited in the quarter₹12,407.15 lakh (₹124.07 crore)
Project bank account (escrow): withdrawn in the quarter₹7,860 lakh (₹78.6 crore)
Project bank account (escrow): balance at quarter end₹18,053.76 lakh (₹180.54 crore)
Units in the project (apartments / plots)1347 apartments
Sold in the quarter155 apartments
EDC (development charges): paid / due as on date₹6,573 lakh (₹65.73 crore) paid; ₹5,803 lakh (₹58.03 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 11-08-2025
  • Zoning Plan: Obtained Approval 26-06-2025
  • Site Plans: Obtained Approval 16-10-2025
  • Building Plans: Obtained Approval 16-10-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Oct 2026, for 30 Sep 2026
By part
  • Tower A: 0%
  • Tower B1: 0%
  • Tower B2: 0%
  • Tower B3: 0%

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against MAX ESTATES GURGAON TWO LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in