RERA’d by NeevHQ

Projects · AMBIENCE DEVELOPERS & INFRASTRUCTURE PVT. LTD.

EWS

Ambience Developers & Infrastructure · Ambience Island, Village Nath Upur, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

Location

Location shown for the area; the exact site was not found.

The builder: Ambience Developers & Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameEWS
Builder (promoter)AMBIENCE DEVELOPERS & INFRASTRUCTURE PVT. LTD.
LocationAMBIENCE ISLAND, VILLAGE NATH UPUR, GURUGRAM
RERA project IDRERA-GRG-569-2020
Registration certificate number319 OF 2017 DATED 23.10.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/03/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2222 acres
Licence16 of 2004 (05-02-2004)
Estimated cost of the project₹4,500 lakh (₹45 crore)
Total units (plots, apartments, shops)560
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered0
Units unsold when registered560
Layout plan approved on10-09-2013
Building plans approved on10-09-2013

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-03-2022
Revised completion date31-03-2022
Infrastructure: projected completion31-03-2022
Infrastructure: percentage complete when registered80%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on20-Aug-2026
Quarterly reports listed on the portal31

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹26.15 lakh (₹0.26 crore)
Spent on construction of apartments in the quarter₹2,176.05 lakh (₹21.76 crore)
Spent on infrastructure in the quarter₹805.94 lakh (₹8.06 crore)
Other costs in the quarter (EDC, taxes, etc.)₹612.52 lakh (₹6.13 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)560 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Zoning Plan: Obtained Approval 09-11-2004
  • Site Plans: Obtained Approval 09-09-2013
  • Building Plans: Obtained Approval 09-11-2013
  • Fire NOC: Obtained Approval 09-11-2013

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 19 Nov 2025
Unclear in the certificate
  • The document is a financial viability statement from a Chartered Accountant firm, not an architect's certificate. It gives no construction completion percentages.
  • The statement covers the period 1 Apr 2024 to 31 Mar 2025 and does not name a quarter.
  • It gives cost figures in INR lakh: cost incurred at period end 3509.40 and estimated cost to complete 990.60. These are costs, not percentages of work done.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 2; Pending: 2; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against AMBIENCE DEVELOPERS & INFRASTRUCTURE PVT. LTD. (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in