Projects · HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED

Express Greens

Haryana State Industrial & Infrastructure Development Corporation · SECTOR-M1A Imt Manesar, Gurugram

Registered with RERA: Sep 2022

Is it legal?

Will it be delivered on time?

Location

The builder: Haryana State Industrial & Infrastructure Development Corporation

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameEXPRESS GREENS
Builder (promoter)HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED
LocationSECTOR-M1A IMT MANESAR
RERA project IDRERA-GRG-1125-2022
Registration certificate numberGGM/609/341/2022/84 DATED 19.09.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area19.64 acres
LicenceLC-1227-VOL-II-JE(VA)/2019/1372-1388 DATE 16.01.2019
Estimated cost of the project₹35,073.9 lakh (₹350.74 crore)
Total units (plots, apartments, shops)972
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered818
Units unsold when registered154
Layout plan approved on22-09-2009
Building plans approved on22-09-2009

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-07-2026
Revised completion date31-07-2026
Infrastructure: projected completion31-07-2026
Infrastructure: percentage complete when registered80%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against HARYANA STATE INDUSTRIAL & INFRASTRUCTURE DEVELOPMENT CORPORATION LIMITED (all its projects)4 (Complaint: 4)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026