RERA’d by NeevHQ

Projects · ANGLE INFRASTRUCTURE PVT. LTD.

Florence Estate

Angle Infrastructure · Sector 70, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Angle Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameFLORENCE ESTATE
Builder (promoter)ANGLE INFRASTRUCTURE PVT. LTD.
LocationSECTOR 70, GURUGRAM
RERA project IDRERA-GRG-618-2020
Registration certificate number287 OF 2017 DATED 10.10.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2018
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area13.455 acres
Licence170 of 2008
Estimated cost of the project₹45,296.23 lakh (₹452.96 crore)
Total units (plots, apartments, shops)292
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder3 BHK: 1,129–1,205 sq ft carpet, 144 units; 3 BHK + study: 1,300 sq ft carpet, 148 units (source: the builder's registration form (Form A-H))
Units booked when registered258
Units unsold when registered36
Layout plan approved on01-12-2013
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2018
Revised completion date31-10-2020
Infrastructure: projected completion31-10-2020
Infrastructure: percentage complete when registered31.89%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against ANGLE INFRASTRUCTURE PVT. LTD. (all its projects)27 (Complaint: 22; Execution of an earlier order: 4; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in