Gardencity Arcade

DLF Utilities · Sector 92, Gurugram

Registered with RERA: Feb 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: DLF Utilities

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameGARDENCITY ARCADE
Builder (promoter)DLF UTILITIES LIMITED
LocationSECTOR 92, GURUGRAM
RERA project IDRERA-GRG-980-2021
Registration certificate numberGGM/537/269/2022/12 DATED 21.02.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to29/04/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.42 acres
LicenceLicense 59 of 2011
Estimated cost of the project₹6,825.19 lakh (₹68.25 crore)
Total units (plots, apartments, shops)89
Unit sizes (carpet area, as declared)2 units of 57 sq ft carpet; 1 unit of 98 sq ft carpet (1 tower); 1 unit of 120 sq ft carpet (1 tower); 1 unit of 147 sq ft carpet (1 tower); 1 unit of 170 sq ft carpet (1 tower); 1 unit of 186 sq ft carpet (1 tower); 3 units of 204 sq ft carpet; 2 units of 208 sq ft carpet; 1 unit of 214 sq ft carpet (1 tower); 1 unit of 216 sq ft carpet (1 tower); 1 unit of 220 sq ft carpet (1 tower); 1 unit of 230 sq ft carpet (1 tower); 1 unit of 231 sq ft carpet (1 tower); 1 unit of 279 sq ft carpet (1 tower); 1 unit of 286 sq ft carpet (1 tower); 1 unit of 310 sq ft carpet (1 tower); 1 unit of 330 sq ft carpet (1 tower); 1 unit of 331 sq ft carpet (1 tower); 1 unit of 336 sq ft carpet (1 tower); 1 unit of 337 sq ft carpet (1 tower); 1 unit of 339 sq ft carpet (1 tower); 1 unit of 345 sq ft carpet (1 tower); 1 unit of 346 sq ft carpet (1 tower); 2 units of 350 sq ft carpet; 1 unit of 396 sq ft carpet (1 tower); 1 unit of 403 sq ft carpet (1 tower); 1 unit of 414 sq ft carpet (1 tower); 1 unit of 424 sq ft carpet (1 tower); 1 unit of 425 sq ft carpet (1 tower); 1 unit of 436 sq ft carpet (1 tower); 3 units of 470 sq ft carpet; 1 unit of 477 sq ft carpet (1 tower); 1 unit of 488 sq ft carpet (1 tower); 3 units of 494 sq ft carpet; 1 unit of 554 sq ft carpet (1 tower); 1 unit of 555 sq ft carpet (1 tower); 1 unit of 565 sq ft carpet (1 tower); 1 unit of 571 sq ft carpet (1 tower); 1 unit of 587 sq ft carpet (1 tower); 1 unit of 593 sq ft carpet (1 tower); 2 units of 611 sq ft carpet; 1 unit of 615 sq ft carpet (1 tower); 3 units of 618 sq ft carpet; 1 unit of 636 sq ft carpet (1 tower); 1 unit of 646 sq ft carpet (1 tower); 1 unit of 660 sq ft carpet (1 tower); 2 units of 664 sq ft carpet; 4 units of 667 sq ft carpet; 1 unit of 676 sq ft carpet (1 tower); 1 unit of 745 sq ft carpet (1 tower); 1 unit of 765 sq ft carpet (1 tower); 1 unit of 772 sq ft carpet (1 tower); 1 unit of 778 sq ft carpet (1 tower); 1 unit of 806 sq ft carpet (1 tower); 1 unit of 809 sq ft carpet (1 tower); 3 units of 810 sq ft carpet; 2 units of 812 sq ft carpet; 3 units of 813 sq ft carpet; 1 unit of 814 sq ft carpet (1 tower); 1 unit of 828 sq ft carpet (1 tower); 1 unit of 835 sq ft carpet (1 tower); 1 unit of 866 sq ft carpet (1 tower); 1 unit of 929 sq ft carpet (1 tower); 1 unit of 982 sq ft carpet (1 tower); 1 unit of 1,120 sq ft carpet (1 tower); 1 unit of 2,036 sq ft carpet (1 tower); 1 unit of 2,568 sq ft carpet (1 tower); 1 unit of 9,577 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-07-2020
Building plans approved on13-01-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction15-04-2022
Likely completion date29-04-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2025 (JUL-SEP)
Latest report submitted on13-Oct-2025
Quarterly reports listed on the portal14

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2025 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹404.84 lakh (₹4.05 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹4,015.02 lakh (₹40.15 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,705.49 lakh (₹17.05 crore)
Project bank account (escrow): deposited in the quarter₹358.87 lakh (₹3.59 crore)
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹1,878.34 lakh (₹18.78 crore)
Units in the project (apartments / plots)99 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 09-07-2021
  • Zoning Plan: Obtained Approval 09-07-2021
  • Service Plans: Obtained Approval 28-10-2014
  • Site Plans: Obtained Approval 13-01-2022
  • Building Plans: Obtained Approval 13-01-2022
  • Fire NOC: Obtained Approval 05-03-2024

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Oct 2025, for 30 Sep 2025
By part
  • One Tower with 99 commercial units: 100%, Table A shows sub-structure, super-structure, MEP and finishing components at 100%. Common area and tower items in Table B are marked completed. Within-unit installations (doors and window panels, sanitary fixtures, modular kitchen, unit electrical fittings, gas piping) and unit flooring are shown as not applicable.
Unclear in the certificate
  • The certificate does not give one overall percentage for the project. Table A gives 100% for each component, but it is not clear how this applies to unit-level fit-out, which is marked not applicable.
  • Table B marks some items as not proposed or not applicable, including open parking, parks and playgrounds, benches, solid waste management and the sewage treatment plant.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DLF UTILITIES LIMITED (all its projects)9 (Complaint: 8; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026