RERA’d by NeevHQ

Projects · GCC INFRA

Global Heights 88A

Gcc Infra · Sector 48, Gurugram

Registered with RERA: Feb 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Gcc Infra

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameGLOBAL HEIGHTS 88A
Builder (promoter)GCC INFRA
LocationP903-905, SECTOR 48, JMD MEGA POLIS, GURUGRAM
RERA project IDRERA-GRG-992-2021
Registration certificate numberGGM/532/264/2022/07 DATED 01.02.2022
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to23/09/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area6.50 acres
Licence77 OF 2021
Estimated cost of the project₹21,582.52 lakh (₹215.83 crore)
Total units (plots, apartments, shops)1022
Unit sizes (carpet area, as declared)86 units averaging about 200 sq ft carpet (33 towers); 936 units averaging about 620 sq ft carpet (8 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-06-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-06-2022
Likely completion date23-09-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on15-Jul-2026
Quarterly reports listed on the portal17

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹86.38 lakh (₹0.86 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹206.36 lakh (₹2.06 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹8.54 lakh (₹0.09 crore)
Project bank account (escrow): deposited in the quarter₹134.37 lakh (₹1.34 crore)
Project bank account (escrow): withdrawn in the quarter₹134.37 lakh (₹1.34 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)Not found in the records checked
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 29-09-2021
  • Zoning Plan: Obtained Approval 29-09-2021
  • Building Plans: Obtained Approval 18-01-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Jun 2026, for 30 Jun 2026
By part
  • Tower 1 to 8 & Commercial Block - Sub structure: 100%, Excavation and raft foundation complete; waterproofing 100%
  • Tower 1 to 8 & Commercial Block - Super structure: 100%, 125 slabs laid; walls on 117 floors; S+14 (7 towers) and S+19 (one tower)
  • Tower 1 to 8 & Commercial Block - Mechanical MEP: 100%
  • Tower 1 to 8 & Commercial Block - Electrical MEP: 100%
  • Tower 1 to 8 & Commercial Block - Plumbing and firefighting: 100%
  • Tower 1 to 8 & Commercial Block - Internal finishing: 100%
  • Tower 1 to 8 & Commercial Block - External finishing: 100%
  • Tower 1 to 8 & Commercial Block - Internal walls (within flat): 45%
  • Tower 1 to 8 & Commercial Block - External walls: 82%
  • Internal roads and pavements: 100%
  • Parks and playgrounds: 99%
  • Shopping area: 98%
  • Street lighting/electrification: 100%
  • Treatment and disposal of sewage and sullage water/STP: 98%
  • Water conservation, rain water harvesting: 100%
  • Electrical meter room, sub-station, receiving station: 96%
  • Community centre: 99%
  • Others (Aaganwadi): 99%
Unclear in the certificate
  • Table A1 shows super structure at 100% cumulative, but Table A item 16 shows internal walls at 45% and external walls at 82% within flats.
  • The MEP heading is numbered '0.53.' in the certificate, which looks garbled.
  • The number of basements field is blank; basement level 2 has no entry, and basement level 1 is marked N/A.
  • The certificate gives no single overall percentage of construction complete or work done in the quarter.
  • Table B has no percentage for parking, solid waste management, energy management and fire protection.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusOnline Complaint Not Yet Received At Office: 1; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against GCC INFRA (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in