Projects · GODREJ DEVELOPERS & PROPERTIES LLP
Godrej Air Phase-I
Godrej Developers & Properties · Sector 85, Gurugram
Registered with RERA: Dec 2018
Is it legal?
- RERA registered, valid till Jun 2027
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit quarterly progress reports (QPRs), per the show-cause notice (open)
- 3 more cases: reply 4
- 4 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Jan 2029, extended 2 times to Jun 2027
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Money: ₹188.7 crore spent of ₹216 crore; ₹27.3 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 179 units: 176 sold, 3 unsold (builder's certificate, Sep 2026)
- Registration now covers 179
- 179 units in 5 sizes, as declared to HRERA:
- 78 units of 895 sq ft carpet (1 tower)
- 1 unit of 904 sq ft carpet (1 tower)
- 2 units of 994 sq ft carpet (1 tower)
- 48 units of 1,371 sq ft carpet (1 tower)
- 50 units of 1,654 sq ft carpet
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 19 km by road (51 min by car)
- Cyber City 58 min · Airport 42 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Godrej Developers & Properties
- 4 projects registered in Gurugram
- 0 with an occupation certificate on record
- 8 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GODREJ AIR PHASE-I |
|---|
| Builder (promoter) | GODREJ DEVELOPERS & PROPERTIES LLP |
|---|
| Location | SECTOR-85, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-7-2018 |
|---|
| Registration certificate number | GGM/300/2018/32 DATED 07.12.2018 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 29/06/2027 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 5.417 acres |
|---|
| Licence | 115 of 2012 |
|---|
| Estimated cost of the project | ₹18,861 lakh (₹188.61 crore) |
|---|
| Total units (plots, apartments, shops) | 179 |
|---|
| Unit sizes (carpet area, as declared) | 78 units of 895 sq ft carpet (1 tower); 1 unit of 904 sq ft carpet (1 tower); 2 units of 994 sq ft carpet (1 tower); 48 units of 1,371 sq ft carpet (1 tower); 50 units of 1,654 sq ft carpet |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 28-09-2018 |
|---|
| Building plans approved on | 28-09-2018 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 15-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 31 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹267.42 lakh (₹2.67 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹18,597.85 lakh (₹185.98 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹10,082.94 lakh (₹100.83 crore) |
|---|
| Spent on infrastructure in the quarter | ₹639.26 lakh (₹6.39 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹8,143.08 lakh (₹81.43 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹187.2 lakh (₹1.87 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹195.58 lakh (₹1.96 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 179 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,105.25 lakh (₹11.05 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 31-10-2018
- Demarcation Plan: Obtained Approval 16-11-2012
- Zoning Plan: Obtained Approval 16-11-2012
- Service Plans: Obtained Approval 11-06-2019
- Electricity Plans: Obtained Approval 31-10-2018
- Site Plans: Obtained Approval 31-10-2018
- Building Plans: Obtained Approval 31-10-2018
- Fire NOC: Obtained Approval 11-03-2019
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 06 Oct 2026, for Oct-26 (Q2 FY 2026-27) |
|---|
| By part | - Building/Tower A4: Structure up to the 25th slab (terrace) for 24 floors above ground. Basement levels 1 and 2 at 100%. Door frames up to the 22nd floor and window frames up to the 13th floor. Internal wall finishing and flooring up to the 24th floor. Lifts installed. Compound wall at 100%.
- Building/Tower A3: Structure up to the 20th slab (terrace) for 19 floors above ground. Basement levels 1 and 2 at 100%. Walls, staircase and lift wells up to the 20th floor. Door and window frames up to the 20th floor. Internal wall finishing, tiling and flooring up to the 19th floor. Lifts installed. Compound wall at 100%.
|
|---|
| Unclear in the certificate | - The certificate does not give one overall percentage for the project or for each tower. It gives percentages per task, so the overall figure is left blank.
- Tower A4 MEP rows have garbled column text (for example 'Upto 24th' and 'Internal Externa l works'), so the MEP percentages are not fully clear.
- Tower A3 waterproofing of the sub-structure is shown as 0 while the Tower A4 entry is 100%. The Tower A3 entry may be a typing error.
- Tower A3 table numbering runs from 19 to 38 and the Tower A3 MEP rows are partly garbled.
- The Pile entries show 0 with no description, so it is not clear whether piling applies to this project.
- The Tower A3 mechanical and electrical rows show different floor ranges from the plumbing row, and the terms are inconsistent.
- The HARERA registration number is written with spaces, and the item numbers in section 1 of the certificate include an irregular numbering sequence.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 07 of 2025 dated 20 Feb 2025: registration extended from 31 Dec 2023 to 29 Jun 2025. Conditions include: The promoter must offer to execute and register a conveyance deed in favour of the allottee(s) for the unit or apartment.; If taxes, charges, fees or levies increase after the scheduled completion date, the extra amount shall not be charged to the allottees.; The extension is granted without prejudice to allottees' rights under section 18, as the promoter failed to prove reasonable circumstances and fault-free reasons for not completing the project within the declared timeline.; The promoter must comply with the Act, the rules and regulations, and other applicable laws. If conditions are not met, the Authority may take action, including revoking the registration.
- Extension 07 of 2025 dated 03 Jul 2025: registration extended from 29 Jun 2025 to 29 Jun 2027. Conditions include: Promoter must pay Rs 25 lakhs penalty for violating section 4(2)(l)(c); the document says it was deposited by DD dated 27.06.2025.; Sale is on carpet area basis only, and the total sale price must include all charges. No separate EDC/IDC is payable beyond the total sale consideration.; Allottees' rights under section 18(1) to delay possession charges are not affected. Promoter must pay delay charges from its own funds, not project cash inflow.; Individual handover dates in BBAs already signed will not change if they fall before the possession date in the DPI.; Promoter must enable formation of an association of allottees within three months of majority booking.; Promoter must submit a monthly comparison of proposed work (PERT chart) and actual work by the 7th day of each month.; Promoter must submit an affidavit on quarterly progress reports and must submit occupation and completion certificates when granted.; Promoter must not create further encumbrance on future receivables or RERA accounts, except the existing lender charge.; Authority may appoint a commissioner to monitor the project and may revoke registration if conditions are not met.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 4 |
|---|
| By status | Scrutinized: 1; First Hearing: 3 |
|---|
| Proceedings | - RERA-GRG-2156-2020: The Authority started its own proceeding against Godrej Developers & Properties LLP, the promoter, through a notice dispatched on 05 Aug 2020. The case page shows it was scrutinized, and no hearing date is fixed. Status: Scrutinized. No next hearing date is fixed (shown as NA). The case page lists a hearing entry dated 14 Aug 2020 with status 'HARERA NEW COMPLAINT'. Latest: 14 Aug 2020, The case page lists a hearing entry on this date with status 'HARERA NEW COMPLAINT'. The Dak ID is 9422. No proceedings or order are recorded for it.
- RERA-GRG-3407-2022: Authority-initiated show cause proceeding against Godrej Developers & Properties LLP (the promoter), under section 4(2)(l)(d), on compliance. The page does not state the grounds of the show cause notice. Status: Listed as at first hearing. The promoter filed a reply to the show cause notice on 20 Jan 2023. No order or proceedings of the day are recorded on the page. Latest: 20 Jan 2023, Promoter's representative filed a reply to the show cause notice.
- RERA-GRG-3601-2022: The Authority issued a show cause notice to the promoter, Godrej Developers & Properties LLP, for not submitting quarterly progress reports (QPRs). The Authority started this case itself. The reply mentions QPRs for June 2022, March 2022, December 2021, June 2021, December 2020, September 2020, June 2020 and March 2020. Status: First hearing was listed for 27 Jun 2022. The record shows only 'FIRST HEARING' with no proceedings or order recorded. The promoter's reply to the show cause notice was received on 08 Dec 2022. Latest: 08 Dec 2022, Promoter's reply to the show cause notice received, covering the QPRs for June 2022, March 2022, December 2021, June 2021, December 2020, September 2020, June 2020 and March 2020.
- RERA-GRG-4339-2022: Project RC compliance hearing concerning Godrej Developers & Properties LLP, Gurugram. The case page is headed HARERA GURUGRAM THROUGH a named complainant V/S GODREJ DEVELOPERS & PROPERTIES LLP. The page lists the party as Self and the case as a complaint, and the Authority issued show cause notices. Status: First hearing listed for 01 Jul 2022. The page shows the status as FIRST HEARING, with no order uploaded. Latest: 25 Jul 2022, Reply to the show cause notice dated 15.06.2022 received (Dak ID 38471), submitted by a representative of the promoter.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 4 |
|---|
| Cases | |
|---|
| Decided cases against GODREJ DEVELOPERS & PROPERTIES LLP (all its projects) | 8 (Complaint: 7; Compensation: 1) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026