RERA’d by NeevHQ

Projects · WONDER CITY BUILDCON LIMITED

Godrej Aria & 101 (Vol. II)

Wonder City Buildcon · Sector 79, Gurugram

Registered with RERA: Sep 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Wonder City Buildcon

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameGODREJ ARIA & 101 (VOL. II)
Builder (promoter)WONDER CITY BUILDCON LIMITED
LocationSEC 79, NAURANGPUR
RERA project IDRERA-GRG-947-2021
Registration certificate numberGGM/746/478/2023/90 DATED 18.09.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/08/2028
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area0.9875 acres
Licence47 of 2013 dated 06.06.2013(14.59375 acres) 109 of 2014 dated 14.08.2014 (2.8375 acres)
Estimated cost of the project₹11,147.43 lakh (₹111.47 crore)
Total units (plots, apartments, shops)56
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 1 unit; 3.5 BHK: 55 units (source: the builder's registration form (Form A-H))
Units booked when registered0
Units unsold when registered56
Layout plan approved on10-02-2020
Building plans approved on10-02-2020

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date28-02-2021
Revised completion date31-08-2028
Infrastructure: projected completion14-02-2028
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal12

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹106.34 lakh (₹1.06 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1.07 lakh (₹0.01 crore)
Spent on infrastructure in the quarter₹2.01 lakh (₹0.02 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1.36 lakh (₹0.01 crore)
Project bank account (escrow): deposited in the quarter₹74.44 lakh (₹0.74 crore)
Project bank account (escrow): withdrawn in the quarter₹69 lakh (₹0.69 crore)
Project bank account (escrow): balance at quarter end₹5.48 lakh (₹0.05 crore)
Units in the project (apartments / plots)56 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹397.49 lakh (₹3.97 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 14-08-2014
  • Demarcation Plan: Obtained Approval 14-08-2014
  • Zoning Plan: Obtained Approval 14-08-2014
  • Service Plans: Obtained Approval 08-03-2018
  • Electricity Plans: Obtained Approval 30-08-2017
  • Site Plans: Obtained Approval 14-08-2014
  • Building Plans: Obtained Approval 14-08-2014
  • Fire NOC: Obtained Approval 14-08-2014

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for Q2 till Sep 2026
Overall work complete26.02%
By part
  • Godrej 101 - Tower-7: Sub structure 95%, super structure 8%, MEP 0%, finishing 0%. Excavation and raft foundation 100%. One basement level and the ground floor 100%. Tower has 15 floors (B+G+13), with 1 slab laid by end of quarter. Walls, staircase, lift wells, plastering, flooring and installations are 0%.
Unclear in the certificate
  • The 35% figure next to the floor count and slab count in the sub-structure and super-structure tables is not clearly labelled.
  • The cumulative work done value column is blank.
  • The validity date of the architect's council registration is blank.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against WONDER CITY BUILDCON LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in