Projects · GODREJ REAL VIEW DEVELOPERS PVT. LTD.
Godrej Meridien- II
Godrej Real View Developers · Sector 106, Gurugram
Registered with RERA: May 2018
Is it legal?
- RERA registered, valid till Dec 2027
- HRERA has opened 5 cases of its own against the builder over this project (4 open, 1 closed):
- Did not file REP-I (Part A to H) on the Authority's web portal for offline registered project (Jun 2022, open)
- Failed to submit quarterly progress report; Authority issued show-cause notices (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, closed)
- 2 more cases: reply 4
- 4 complaints about this project decided by HRERA since Nov 2023 (4 delay interest ordered)
Will it be delivered on time?
- Original deadline Sep 2023, extended 2 times to Dec 2027
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Sep 2024) covers: Towers 3 and 7 and part basement (232 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- Money: ₹238.5 crore spent of ₹270.1 crore; ₹31.6 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 134 units: 133 sold, 1 unsold (builder's certificate, Sep 2026)
- Apartment: 133 of 134 sold
- Commercial Shops: 0 of 0 sold
- EWS: 0 of 0 sold
- Registration now covers 1 residential tower with 134 residential units
- 134 units, as declared to HRERA:
- 134 units averaging about 1,480 sq ft carpet (1 tower)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 10.3 km by road (16 min by car)
- Cyber City 55 min · Airport 34 min by car at 9:30 am
- Within 3 km: 3 hospitals, 0 schools, 0 malls
The builder: Godrej Real View Developers
- 3 projects registered in Gurugram
- 3 with an occupation certificate on record
- 31 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GODREJ MERIDIEN- II |
|---|
| Builder (promoter) | GODREJ REAL VIEW DEVELOPERS PVT. LTD. |
|---|
| Location | SECTOR-106,BABUBPUR, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-436-2019 |
|---|
| Registration certificate number | GGM/274/2018/06 DATED 18.05.2018 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 31/12/2027 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|
| Land area | 14.793 acres |
|---|
| Licence | 18 of 2008 (15.02.2020) |
|---|
| Estimated cost of the project | ₹25,798 lakh (₹257.98 crore) |
|---|
| Total units (plots, apartments, shops) | 134 |
|---|
| Unit sizes (carpet area, as declared) | 134 units averaging about 1,480 sq ft carpet (1 tower) |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | Not applicable (new project) |
|---|
| Units unsold when registered | Not applicable (new project) |
|---|
| Layout plan approved on | 14-03-2019 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 13-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹6.94 lakh (₹0.07 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹480.53 lakh (₹4.81 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0.85 lakh (₹0.01 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹6.94 lakh (₹0.07 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹6.94 lakh (₹0.07 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 134 apartments |
|---|
| Sold in the quarter | 134 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹183.68 lakh (₹1.84 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 21-03-2018
- Demarcation Plan: Obtained Approval 24-10-2016
- Zoning Plan: Obtained Approval 24-10-2016
- Service Plans: Obtained Approval 25-06-2018
- Electricity Plans: Obtained Approval 21-03-2018
- Site Plans: Obtained Approval 21-03-2018
- Building Plans: Obtained Approval 21-03-2018
- Fire NOC: Obtained Approval 18-05-2023
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 01 Oct 2026, for Q2 (FY 2026-27) |
|---|
| By part | - Tower 3 (2B+G+34), sub structure: 100%
- Tower 3, super structure: 100%, Terrace floor completed; 34 floors excluding ground floor
- Tower 3, MEP (mechanical, electrical, plumbing and firefighting): 100%
- Tower 3, finishing (internal and external): 100%
- Tower 3, compound wall: 100%
- Internal roads and pavements: 100%
- Parking (covered and open): 100%
- Landscaping and tree plantation: 100%
- Parks and playgrounds: 100%
- Water supply: 100%
- Sewerage: 100%
- Storm water drains: 100%
- Energy management (solar): 100%
- Fire protection and fire safety: 100%
- Electrical meter room, sub-station, receiving station: 100%
|
|---|
| Unclear in the certificate | - The certificate lists the cumulative number of slabs laid as '2' next to 'Terrace Floor Completed', which does not clearly match a 34-floor tower.
- Table B-4 shows 'Cumulative Progress 100%' for services to be transferred to the competent authority. It is not clearly the overall project figure, so no overall percentage was filled.
- Several items in Table B have no percentage or are marked NA or dashes, so they are not listed.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 14 of 2024: registration extended from 30 Sep 2023 to date not stated. Conditions include: The extension is granted without prejudice to the rights of allottees under section 18 of the Act.; The extension is granted because the promoter failed to prove reasonable circumstances and found it hard to complete the project in the time declared under section 4(2)(l)(C).; The promoter shall offer to execute and register conveyance deeds in favour of allottees.; No taxes, charges, fees or levies arising after the expiry of the scheduled completion date shall be charged from allottees, and this extension of registration shall not be a reason for such charges.; The promoter shall comply with the provisions of the Act and the rules and regulations made under it.; The promoter shall not contravene any other law in force that applies to the project.; If the conditions are not fulfilled, the Authority may take action, including revoking the registration.
- Extension 14 of 2024 dated 27 Aug 2025: registration extended from 28 Mar 2025 to 31 Dec 2027. Conditions include: Registration remains in force from 29 Mar 2025 to 31 Dec 2027, subject to the terms stated, and is binding on the promoter.; The promoter must deposit a penalty of Rs. 25 lakhs for violation of sections 3 and 4 of the Act. The document records a DD of Rs. 25,00,000 dated 07 Aug 2025 as submitted.; The promoter must pay delay possession charges under section 18(1) from the promoter's own funds. Project cash inflow shall not be used for this purpose.; The promoter must deposit 100% of amounts realised from allottees in a separate account to cover construction cost and proportionate land cost.; No subvention scheme or assured return scheme may be run for the project without prior approval of the Authority.; The promoter must submit quarterly progress reports and a monthly comparison of proposed and actual work by the 7th of each month.; The promoter must get accounts audited within six months after each financial year end by a chartered accountant.; The promoter must take approvals and renewals on time. Some licences and approvals will expire before the project completion date.; Sale is on carpet area basis and the total sale consideration includes all charges. No separate EDC/IDC is payable beyond the total sale consideration.; The promoter must not accept more than ten percent of the cost as advance before a registered written agreement for sale.; The Authority may take action, including revoking registration, if conditions are not met.; The promoter must submit an occupation certificate copy and the declaration deed to the competent authority once granted.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 5 |
|---|
| By status | First Hearing: 3; Disposed: 1; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2586-2022: Non-filing of REP-I (Part A to H) on the Authority's web portal for an offline registered project, either with the Interim Real Estate Regulatory Authority, Panchkula, or HRERA Gurugram. Status: First hearing listed for 29 Jun 2022 at 11:00 am at HARERA Gurugram. No hearing proceedings, bench order or order upload is recorded in the document. Latest: 29 Jun 2022, First hearing was scheduled at 11:00 am at HARERA Gurugram. The case status is recorded as First Hearing, with no proceedings of the day recorded.
- RERA-GRG-3326-2024: Suo motu case by the Authority on an alleged violation of section 4(2)(l)(C) of the Act for the project Godrej 24 K (Phase 2), where the project's registration certificate had expired. The promoter is Godrej Real View Developers Pvt. Ltd. Status: Disposed. The Authority closed the matter on 06 Sep 2024 after recording that the registration of the project had been extended till 28 Mar 2025. Latest: 06 Sep 2024, The final judgement was uploaded. The judgement lists the Authority as the party and the promoter as the other party. Outcome: Disposed of on 06 Sep 2024. The Authority recorded that the project's registration had been extended under section 6 for one year, till 28 Mar 2025.
- RERA-GRG-3368-2022: Authority's proceeding against the promoter arising from a show cause notice under section 4(2)(l)(d) for financial year 2020-21 Status: Listed as at first hearing, with a next hearing date of 30 Jun 2022. No order is uploaded. The latest entry is the promoter's reply to the show cause notice, received 04 Jan 2023. Latest: 04 Jan 2023, Promoter's reply to the show cause notice received by the Authority.
- RERA-GRG-3574-2022: The Authority issued show cause notices to the promoter, Godrej Real Estate Developers Pvt. Ltd., for not submitting its quarterly progress report. The Authority started this case itself, and the promoter was asked to appear before it on 27 Jun 2022 with a written reply. Status: First hearing listed for 27 Jun 2022. The page shows no proceedings, bench order or outcome for that hearing. Latest: 27 Jun 2022, First hearing was scheduled at 11.00 am in the Authority's office in Gurugram. The promoter was asked to appear with a written reply if it had anything to say. The listing shows the status as First Hearing, with no proceedings or order recorded.
- RERA-GRG-5636-2019: The Authority's own proceeding against the promoter Godrej Real Developers Pvt. Ltd. about notices under Section 42 of the RERA Act, including the quarterly progress report (QPR) and scrutiny of the REP-I Part A-H documents. Status: Pending. The case page shows the status as PENDING. The last hearing listed is 17 Feb 2020, with no order recorded for that date. A reply to a show cause notice (A to H) was received on 04 Jan 2023. No later order is shown. Latest: 04 Jan 2023, Reply to show cause notice (A to H) received from the promoter's side (Dak ID 46923).
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 4 |
|---|
| Cases | |
|---|
| Decided cases against GODREJ REAL VIEW DEVELOPERS PVT. LTD. (all its projects) | 31 (Complaint: 31) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in