Projects · GODREJ PROJECTS DEVELOPMENT PVT LTD
Godrej Summit
Godrej Projects Development · Sector 104, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Sep 2018 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Part A to H) on Authority web portal for offline-registered project (Jun 2022, open)
- Did not apply for registration extension, completion or occupation certificate, or required documents (Jun 2022, open)
- Did not complete project within the completion period it declared (Jun 2022, open)
- 4 more cases: reply 4
- 14 complaints about this project decided by HRERA since Nov 2023 (5 refund ordered, 9 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Dec 2018, never extended (date has passed)
- Occupation certificate (Dec 2018) covers: High-rise building in Gurugram
- Construction, as certified by the architect (Oct–Dec 2025):
- Done: Tower 1, Common areas and facilities
- Money: ₹126.7 crore spent of ₹126.7 crore (CA certificate, Dec 2025)
What's on offer?
- 184 units: 118 sold, 66 unsold (builder's certificate, Dec 2025)
- Tower-1: 43 of 70 sold
- Tower-4: 70 of 109 sold
- Shops: 5 of 5 sold
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 1 BHK: 419–502 sq ft carpet, 2 units
- 3 BHK: 978–1,194 sq ft carpet, 19 units
- 3 BHK + utility: 1,044–1,048 sq ft carpet, 90 units
- 4 BHK + utility: 1,330 sq ft carpet, 34 units
- 4 BHK + study + utility: 1,541 sq ft carpet, 32 units
Location
- Nearest metro: IFFCO Chowk, 10.4 km by road (42 min by car)
- Cyber City 55 min · Airport 37 min by car at 9:30 am
- Within 3 km: 22 hospitals, 6 schools, 0 malls
The builder: Godrej Projects Development
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 22 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GODREJ SUMMIT |
|---|
| Builder (promoter) | GODREJ PROJECTS DEVELOPMENT PVT LTD |
|---|
| Location | SECTOR 104 GURUGRAM |
|---|
| RERA project ID | RERA-GRG-653-2020 |
|---|
| Registration certificate number | 75 OF 2017 DATED 21.08.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/09/2018 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2.0130 acres |
|---|
| Licence | Licence No 102 of 2011 dated 07.12.2011 |
|---|
| Estimated cost of the project | ₹14,162.37 lakh (₹141.62 crore) |
|---|
| Total units (plots, apartments, shops) | 184 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 1 BHK: 419–502 sq ft carpet, 2 units; 3 BHK: 978–1,194 sq ft carpet, 19 units; 3 BHK + utility: 1,044–1,048 sq ft carpet, 90 units; 4 BHK + utility: 1,330 sq ft carpet, 34 units; 4 BHK + study + utility: 1,541 sq ft carpet, 32 units (source: the builder's registration form (Form A-H)) |
|---|
| Units booked when registered | 109 |
|---|
| Units unsold when registered | 75 |
|---|
| Layout plan approved on | 01-05-2017 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 26-12-2018 |
|---|
| Revised completion date | 26-12-2018 |
|---|
| Infrastructure: projected completion | 26-12-2018 |
|---|
| Infrastructure: percentage complete when registered | 100% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
|---|
| Latest report submitted on | 25-Feb-2026 |
|---|
| Quarterly reports listed on the portal | 29 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 184 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹546.85 lakh (₹5.47 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 20-07-2011
- Zoning Plan: Obtained Approval 08-12-2011
- Service Plans: Obtained Approval 19-01-2015
- Electricity Plans: Obtained Approval 31-03-2015
- Site Plans: Obtained Approval 05-09-2012
- Building Plans: Obtained Approval 05-09-2012
- Fire NOC: Obtained Approval 21-01-2013
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Dec 2025, for Dec-25 |
|---|
| By part | - Tower 1: 100%, Structure, MEP and finishing all shown as 100% complete; G+17 floors, all slabs laid, all listed installation and finishing items completed
- Tower 4: Sub-structure and super-structure 100% complete; internal finishing 95.24%; some unit-level plaster, tiling, flooring and fittings 95.24%; common areas and external works 100%
- Common areas and facilities (Table B): 100%, All listed services, parking and community items marked completed
|
|---|
| Unclear in the certificate | - No single overall percentage is stated for Tower 4; figures are given per activity only.
- Table A pages for Towers 2 and 3 are not in the document.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | First Hearing: 5; Online Complaint Not Yet Received At Office: 1; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2589-2022: The Authority started this case itself against the promoter, Godrej Projects Development Pvt Ltd, for not filing REP-I (Part A to H) on the Authority's web portal for offline registered projects, registered with either the Interim Real Estate Regulatory Authority, Panchkula or HRERA Gurugram. Status: Listed for first hearing on 29 Jun 2022. The page does not record what happened at that hearing, and no order is shown. Latest: 29 Jun 2022, First hearing listed at 11:00 am at HRERA Gurugram. The promoter was asked to appear and say anything it had on the matter.
- RERA-GRG-2713-2022: Case page lists HARERA Gurugram, through a representative, against Godrej Projects Development Pvt Ltd. The page shows no hearings, orders or decisions. Status: The complaint is marked as an online complaint not yet received at the office. It is not yet dispatched, and the next date of hearing is shown as NA.
- RERA-GRG-2898-2022: A show cause notice issued by the Authority to the promoter, Godrej Projects Development Pvt Ltd, for not applying for extension of registration, not submitting a completion, part completion or occupation certificate, and not submitting required documents. Status: The case is listed at the first hearing stage, scheduled for 28 Jun 2022. The listing shows no proceedings or order for that date. The promoter's reply to the show cause notice was received on 18 Nov 2022. Latest: 18 Nov 2022, The promoter's representative submitted a reply to the show cause notice (Dak ID 44277).
- RERA-GRG-2901-2022: The Authority issued a show-cause notice to the promoter, Godrej Projects Development Pvt Ltd, for not completing the project within the time it declared, as required under section 4(2)(l)(C) of the RERA Act. Status: The case page shows the first hearing listed for 30 Jun 2022 with status 'First Hearing'. No proceedings or order are recorded. The promoter's reply to the show-cause notice was received on 18 Nov 2022. Latest: 18 Nov 2022, The promoter's reply to the show-cause notice dated 03 Jun 2022 was received (Dak ID 44276).
- RERA-GRG-2958-2022: Show cause notice to the promoter, Godrej Projects Development Pvt Ltd, for not submitting a quarterly progress report. The Authority asked the promoter to explain or appear at a hearing. Status: First hearing listed for 27 Jun 2022. The page records no proceedings, bench order or order upload for that date. Latest: 27 Jun 2022, First hearing listed. No proceedings or order are recorded on the page.
- RERA-GRG-5113-2022: The case page lists the complaint as HARERA Gurugram through an official against Godrej Projects Development Pvt Ltd. The page does not state what the complaint is about. Status: First hearing listed for 30 Jun 2022. The page shows no proceedings recorded for that day, no order uploaded, and no outcome. Latest: 16 Jul 2022, A document was submitted by the complainant's side under Dak ID 37970, with the remark NEW COMPLAINT.
- RERA-GRG-5273-2019: Failure to file REP-I (Part A to H) online and in hard copy, and to submit Quarterly Progress Report updates, for the Godrej Summit project in Sector 104, Gurugram, which was registered offline. The Authority started the proceeding against the promoter. Status: Pending. The promoter has been directed to file REP-I online and in hard copy. A final personal hearing is fixed for 24 Feb 2020 at 2.00 pm. Latest: 24 Feb 2020, Final personal hearing scheduled before the Authority. Status recorded as pending. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues, cumulatively up to five percent of the estimated cost of the real estate project as determined by the Authority. This was imposed under section 63 of the Act. The case page lists it as decided by the Authority on 15 Jan 2020.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 14 |
|---|
| Cases | - RERA-GRG-4927-2024 (compensation, decided 30-Sep-2026): Buyer sought Rs 30 lakh compensation for harassment; complaint dismissed as not maintainable before the Adjudicating Officer.
- RERA-GRG-4929-2024 (compensation, decided 30-Sep-2026): Buyer sought Rs 16 lakh compensation; Adjudicating Officer dismissed complaint as not maintainable, no compensation ordered.
- RERA-GRG-4924-2024 (compensation, decided 30-Sep-2026): Buyer sought Rs 30 lakh compensation for harassment; complaint dismissed as not maintainable before the Adjudicating Officer.
- RERA-GRG-4925-2024 (compensation, decided 30-Sep-2026): Buyer sought refund after no possession of Godrej Summit unit; complaint dismissed as not maintainable before Adjudicating Officer.
- RERA-GRG-3017-2024 (complaint, decided 27-Jan-2026): Buyer sought refund of paid amount after 2016 cancellation; builder ordered to refund Rs 21.03 lakh minus 10% earnest money with 10.80% interest.
- RERA-GRG-4471-2023 (complaint, decided 10-Sep-2025): Buyers sought refunds for delayed Godrej Summit units; Authority dismissed as not maintainable due to multiple sales and bank claims.
- RERA-GRG-4470-2023 (complaint, decided 10-Sep-2025): Buyers sought refunds for delayed Godrej Summit units; Authority dismissed as not maintainable due to multiple sales and bank claims.
- RERA-GRG-5280-2023 (complaint, decided 10-Sep-2025): Buyers sought refunds for delayed Godrej Summit units; Authority dismissed as not maintainable due to multiple sales and bank claims.
- RERA-GRG-5257-2023 (complaint, decided 10-Sep-2025): Buyers sought refunds for delayed Godrej Summit units; Authority dismissed as not maintainable due to multiple sales and bank claims.
- RERA-GRG-2880-2024 (complaint, decided 08-Aug-2025): Buyer sought refund after possession delay; builders ordered to refund Rs 44.28 lakh with 10.90% interest.
- RERA-GRG-3299-2023 (complaint, decided 16-May-2025): Buyer surrendered flat and sought refund; Authority ordered builder to refund paid amount less 10% with 11.10% interest.
- RERA-GRG-5671-2022 (complaint, decided 05-Jul-2024): Buyer sought refund after possession delay with no occupation certificate; builder ordered to refund Rs 47.3 lakh with 10.95% interest.
- RERA-GRG-1909-2022 (complaint, decided 24-May-2024): Buyers sought delay compensation and refund of Rs 7 lakh; HRERA held no delay case, ordered the Rs 7 lakh adjusted against stamp duty and conveyance deed executed within 3 months.
- RERA-GRG-2134-2021 (complaint, decided 19-Apr-2024): Buyer sought refund after surrendering unit; builder ordered to refund paid amount less 10% with 10.85% interest.
|
|---|
| Decided cases against GODREJ PROJECTS DEVELOPMENT PVT LTD (all its projects) | 22 (Compensation: 6; Complaint: 16) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in