RERA’d by NeevHQ

Projects · GOEL & SON'S DEVELOPERS PRIVATE LIMITED

Golden Park

Goel & Son's Developers · Sector 4, Gurugram

Registered with RERA: Oct 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Goel & Son's Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameGOLDEN PARK
Builder (promoter)GOEL & SON'S DEVELOPERS PRIVATE LIMITED
LocationSECTOR 4, SOHNA
RERA project IDRERA-GRG-1099-2022
Registration certificate numberGGM/614/346/2022/89 DATED 03.10.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to24/06/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area18.025 acres
Licence76 of 2022 (24-06-2022)
Estimated cost of the project₹9,892.99 lakh (₹98.93 crore)
Total units (plots, apartments, shops)324
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on15-07-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction15-07-2022
Likely completion date23-06-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on11-Oct-2026
Quarterly reports listed on the portal15

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹619.54 lakh (₹6.2 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,500 lakh (₹15 crore)
Spent on infrastructure in the quarter₹2,700 lakh (₹27 crore)
Other costs in the quarter (EDC, taxes, etc.)₹9,363.72 lakh (₹93.64 crore)
Project bank account (escrow): deposited in the quarter₹619.54 lakh (₹6.2 crore)
Project bank account (escrow): withdrawn in the quarter₹619.54 lakh (₹6.2 crore)
Project bank account (escrow): balance at quarter end₹4.5 lakh (₹0.05 crore)
Units in the project (apartments / plots)325 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹1,721.77 lakh (₹17.22 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 27-06-2022
  • Demarcation Plan: Obtained Approval 29-09-2022
  • Zoning Plan: Obtained Approval 29-09-2022
  • Service Plans: Obtained Approval 02-01-2023
  • Electricity Plans: Obtained Approval 24-09-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 11 Oct 2026, for 30 Sep 2026
By part
  • Internal roads & pavements: 100%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tank, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation: 100%
  • Parks and playgrounds: 100%
  • Street lighting/electrification: 100%
  • Treatment and disposal of sewage and sullage water/STP: 100%
  • Water conservation, rain water harvesting, percolating well/pit: 100%
  • Fire protection and fire safety requirements: 97%
  • Electrical meter room, sub-station, receiving station: 100%
  • Community centre (to be transferred to RWA): 75%
Unclear in the certificate
  • Table A (tower/building-wise construction status) shows NA for every item, so no tower-wise percentages are given.
  • Table B lists parking, shopping area, solid waste management, energy management and some other items as NA, so no percentage is stated for them.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusDisposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against GOEL & SON'S DEVELOPERS PRIVATE LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in