Registration

Project nameGRACE RESILVIAA
Builder (promoter)HERCULES VENTURES LLP
LocationSECTOR 78, VILLAGE NAURANGPUR , GURUGRAM
RERA project IDRERA-GRG-1899-2025
Registration certificate numberGGM/957/689/2025/60 DATED 17.06.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/09/2029
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.0450 acres
Licence52 of 2023 Granted by Directorate of Town and Country Planning, Chandigarh Haryana, on the date 14.03.2023 valid up to 12.03.2028
Estimated cost of the project₹7,945.88 lakh (₹79.46 crore)
Total units (plots, apartments, shops)170
Unit sizes (carpet area, as declared)136 units of 841 sq ft carpet (34 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on15-03-2023
Building plans approved on23-10-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-04-2025
Likely completion date30-09-2029

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on16-Oct-2026
Quarterly reports listed on the portal5

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹422.68 lakh (₹4.23 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹67.84 lakh (₹0.68 crore)
Spent on construction of apartments in the quarter₹471 lakh (₹4.71 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹41 lakh (₹0.41 crore)
Project bank account (escrow): deposited in the quarter₹422.68 lakh (₹4.23 crore)
Project bank account (escrow): withdrawn in the quarter₹444.16 lakh (₹4.44 crore)
Project bank account (escrow): balance at quarter end₹7 lakh (₹0.07 crore)
Units in the project (apartments / plots)136 apartments, 34 plots
Sold in the quarter7 apartments, 0 plots
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 13 Oct 2026, for July to Sept 2026
By part
  • Sub structure (overall, Table A): 100%, Excavation and raft complete; basement level 1 under progress
  • Super structure (overall, Table A): 50%, Stilt plus 4 floors; walls, staircase and lift wells under progress
  • Electrical (conducting wiring, fixtures): 15%
  • Plumbing and firefighting (piping, pumps, pump room): 20%
  • Excavation: 100%, Complete
  • Raft foundation: 100%, Complete
  • Basement Level 1: 60%, Under progress
  • Waterproofing of sub-structure: not stated
  • Total floors in tower/building: 40%, Stilt plus 4 floors
  • Total area on each floor: 35%, As per building plans
  • Stilt/ground floor: 40%, As per building plans
  • Slabs, floor wise: 40%, As per building plans
  • Walls on floors: 25%, Under progress
  • Staircase: 20%, Under progress
  • Lift wells along with waterproofing: 15%, Under progress
  • Lift lobbies and common areas, floor wise: 10%, Under progress
  • Fixing of door and window frames in units: Not started
  • Underground water tank: 10%, Under progress
  • Status of construction of compound wall: 70%, Under progress
  • Waterproofing of terraces: Not started
  • Entrance lobby finishing: Not started
  • Internal roads and pavements: 20%, Under progress
  • Water supply: 10%, Under progress
  • Sewerage (chamber, lines, septic tanks, STP): 15%, Under progress
  • Storm water drains: 10%, Under progress
  • Treatment and disposal of sewage and sullage water/STP: 10%, Under progress
Unclear in the certificate
  • Table A and the Table B tasks list the project as one building; no tower or block names are given.
  • Items 15 to 20 of the second task table are headed Sub-Structure Status but describe finishing and compound wall work.
  • Table A mechanical and internal/external finishing rows show no figures.
  • No single overall percentage of construction completed is stated in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against HERCULES VENTURES LLP (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026