Projects · ASTER INFRAHOME PVT. LTD.
Green Court
Aster Infrahome · Sector 90, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Jul 2024 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report (open)
- Did not submit completion, part completion or occupation certificate after registration extension expired (Jun 2022, open)
- Did not file REP-I project update forms online and in hard copy, or quarterly progress reports (Nov 2019, open). At stake: ₹25,000 per day from 31 Dec 2019; total may reach 5% of project cost
- 3 more cases: reply 4
- 17 complaints about this project decided by HRERA since Nov 2023 (2 delay interest ordered, 15 refund ordered)
Will it be delivered on time?
- Original deadline May 2020, extended to Jul 2024
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Nov 2022) covers: Towers A to M: 1,658 flats, creche and community hall (1,658 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Electrical 99%, Super structure 97%, Mechanical 97%, Internal finishing 97%, Sub structure 96%, Plumbing and firefighting 94%, and 1 more
- Money: ₹342 crore spent of ₹370 crore; ₹28 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- Registration now covers 1658
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 1 BHK: 636 units
- 2 BHK: 1,022 units
Location
- Nearest metro: Millennium City Centre Gurugram, 21.6 km by road (58 min by car)
- Cyber City 64 min · Airport 49 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Aster Infrahome
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 72 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GREEN COURT |
|---|
| Builder (promoter) | ASTER INFRAHOME PVT. LTD. |
|---|
| Location | SECTOR-90, VILLAGE- HAYATPUR, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-412-2019 |
|---|
| Registration certificate number | 137 OF 2017 DATED 28.08.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 22/07/2024 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 10.0125 acres |
|---|
| Licence | 61, 62 of 2014 dated 07 07 2014 |
|---|
| Estimated cost of the project | ₹297 lakh (₹2.97 crore) |
|---|
| Total units (plots, apartments, shops) | 1658 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 1 BHK: 636 units; 2 BHK: 1,022 units (source: the builder's registration form (Form A-H)) |
|---|
| Units booked when registered | 1613 |
|---|
| Units unsold when registered | 45 |
|---|
| Layout plan approved on | 22-10-2014 |
|---|
| Building plans approved on | 22-10-2014 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 15-05-2020 |
|---|
| Revised completion date | 15-05-2020 |
|---|
| Infrastructure: projected completion | 15-05-2020 |
|---|
| Infrastructure: percentage complete when registered | 15% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 29-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹20 lakh (₹0.2 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹27.09 lakh (₹0.27 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹10.33 lakh (₹0.1 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹11.99 lakh (₹0.12 crore) |
|---|
| Units in the project (apartments / plots) | 1658 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,290.73 lakh (₹12.91 crore) paid; ₹0 due |
|---|
| Approvals listed | Not found in the records checked |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026 |
|---|
| By part | - Sub structure: 96%
- Super structure: 97%
- MEP - Mechanical (lifts, ventilation): 97%
- MEP - Electrical (conduiting, wiring, fixtures): 99%
- MEP - Plumbing and Firefighting (piping, pumps, fixtures): 94%
- Finishing - Internal (plaster, tiling, flooring, painting): 97%
- Finishing - External (plaster, painting, facade): 93%
|
|---|
| Unclear in the certificate | - The tower or building name in Table A is blank, so the tower-wise figures cannot be linked to a named tower.
- The 'Cumulative work done value till date' for internal finishing is written as '96%%'; the 'percentage of work done to total proposed work' column shows 97%, which is used here.
- The certificate does not state the quarter it covers; it refers only to 'the end of the quarter'.
- The overall and in-quarter figures are given per component, not as one overall percentage.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | - Extension of Registration Certificate (Form REP-V, corrigendum/addendum to a registration certificate): The Authority extended the registration of the Green Court affordable group housing project in Sector-90 Gurugram, promoted by Aster Infrahome Private Limited, for one year, valid till 22 January 2021. The registration was granted under section 6 of the Real Estate (Regulation & Development) Act, 2016, under project registration number 2077/137, revised as 2020/09. The extension is subject to these conditions: the promoter must submit a copy of the renewed licence within 3 months of the certificate's issue; submit the occupation certificate when received from the competent authority; offer to execute and register conveyance deeds in favour of allottees; deposit 70 percent of amounts realised from allottees in a separate scheduled bank account to cover construction and land cost, used only for that purpose; and comply with the Act, the rules and regulations, and all other applicable laws. If conditions are not met, the Authority may take action, including revoking the registration. The project covers about 10 acres, has 13 towers, and a total FAR of 90,244.755 sq m.
|
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 2; First Hearing: 3; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2755-2022: A complaint case number RERA-GRG-2755-2022 listed against Aster Infrahome Pvt. Ltd. The page does not state what the complaint is about. Status: The page shows the online complaint has not yet been received at the office. No next hearing date is fixed (Not Yet).
- RERA-GRG-3071-2022: Authority's show cause notice to the promoter Aster Infrahome Pvt. Ltd. for not submitting a quarterly progress report, with a first hearing set for 27 Jun 2022 Status: First hearing listed for 27 Jun 2022. The page records no proceedings of the day and no order. Latest: 27 Jun 2022, First hearing listed before the Authority at HARERA Gurugram. Status shows as First Hearing, with no proceedings or order recorded.
- RERA-GRG-3770-2022: Failure to submit a completion certificate, part completion certificate or occupation certificate after the validity of the project's registration extension expired. The case is against the promoter Aster Infrahome Pvt. Ltd. and was brought by the Authority (HARERA Gurugram). Status: First hearing listed for 11 Jul 2022. The page records no proceedings or order for that hearing. Latest: 11 Jul 2022, First hearing listed. The case page shows the status as First Hearing, with no proceedings of the day, bench order or order uploaded.
- RERA-GRG-3771-2022: The page does not state what the complaint is about. It lists the Authority (HARERA Gurugram) as the party against the promoter, Aster Infrahome Pvt. Ltd. Status: The online complaint has not yet been received at the office. No next hearing date is listed (NA), and the complaint has not been dispatched. The listing table is empty.
- RERA-GRG-4988-2022: A complaint by a home buyer against the promoter Aster Infrahome Pvt Ltd, registered as RERA-GRG-4988-2022. The page shows the case title as a complaint against the promoter, not as a case the Authority started on its own. Status: At first hearing stage. The first hearing was listed for 30 Jun 2022, and the page shows no order uploaded for that hearing. Latest: 16 Jul 2022, Documents were received by the Authority under Dak ID 38084, submitted by the complainant and marked as 'New Complaint'.
- RERA-GRG-5413-2019: The promoter's failure to file the online project update form REP-I (Part A-H), the hard copy with supporting documents, and quarterly progress reports for an affordable group housing project in Sector 90, Gurugram. The Authority started the proceeding itself. Status: Pending. The personal hearing was listed for 24 Feb 2020. The record ends with a fourth notice under Section 42(1D) dispatched on 15 Jul 2020, and no later order is shown. Latest: 15 Jul 2020, Fourth notice dispatched, referred to as a notice under Section 42(1D). Penalty: Rs 25,000 per day, imposed by the Authority's order of 15 Jan 2020, from 31 Dec 2019 while the default continues. The total may extend up to five percent of the estimated project cost, as determined by the Authority.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 17 |
|---|
| Cases | - RERA-GRG-6428-2025 (compensation, decided 30-Oct-2026): Buyer's Rs 3 lakh shop booking had no agreement; builder ordered to pay Rs 4 lakh compensation with 11% interest.
- RERA-GRG-6429-2025 (compensation, decided 30-Oct-2026): Buyer sought compensation over cancelled booking; builder ordered to pay Rs 4 lakh with 11% interest.
- RERA-GRG-1351-2024 (complaint, decided 27-Jan-2026): Buyer's allotment was cancelled for non-payment; HRERA upheld cancellation but ordered builder to refund Rs 21.41 lakh less Rs 25,000 with 10.80% interest.
- RERA-GRG-508-2025 (complaint, decided 13-Jan-2026): Buyer's unit cancelled for unpaid dues; builder ordered to refund paid amount minus Rs 25,000 with 10.80% interest.
- RERA-GRG-509-2025 (complaint, decided 13-Jan-2026): Buyer's allotment cancelled for non-payment; HRERA ordered builder to refund paid amount minus Rs 25,000 with 10.80% interest.
- RERA-GRG-3522-2024 (complaint, decided 23-Dec-2025): Buyers sought refund after cancellation of an affordable flat; builder ordered to refund Rs 19.72 lakh less Rs 25,000 with 10.80% interest.
- RERA-GRG-73-2024 (complaint, decided 09-Jul-2025): Buyer sought unit restoration and possession after cancellation; HRERA upheld cancellation but ordered builder to refund amount paid minus Rs 25,000 with 11.10% interest.
- RERA-GRG-5884-2024 (complaint, decided 04-Jul-2025): Buyer sought possession after cancellation for unpaid dues; HRERA upheld cancellation, ordered refund minus Rs 25,000 with 11.10% interest.
- RERA-GRG-5887-2024 (complaint, decided 04-Jul-2025): Buyer sought possession after cancellation for unpaid dues; HRERA upheld cancellation, ordered refund minus Rs 25,000 with 11.10% interest.
- RERA-GRG-5883-2024 (complaint, decided 04-Jul-2025): Buyer sought possession after cancellation for unpaid dues; HRERA upheld cancellation, ordered refund minus Rs 25,000 with 11.10% interest.
- RERA-GRG-145-2024 (complaint, decided 02-Jul-2025): Buyer sought delay interest after late Green Court flat; builder ordered to hand over possession, pay 11.10% interest, and drop illegal charges.
- RERA-GRG-3751-2023 (complaint, decided 04-Mar-2025): Buyer faced cancellation for non-payment after possession offer; HRERA upheld cancellation and ordered refund minus Rs 25,000 with 11.10% interest.
- RERA-GRG-3752-2023 (complaint, decided 04-Mar-2025): Buyer faced cancellation for non-payment after possession offer; HRERA upheld cancellation and ordered refund minus Rs 25,000 with 11.10% interest.
- RERA-GRG-5406-2022 (complaint, decided 11-Feb-2025): Buyer sought delay interest; builder ordered to pay 11.10% interest on paid amount from Jan 2020 to Jan 2023.
- RERA-GRG-6542-2022 (complaint, decided 05-Jul-2024): Buyer sought refund of Rs 3 lakh booking amount; HRERA ordered builder to refund it with 10.95% interest.
- RERA-GRG-6400-2022 (complaint, decided 05-Jul-2024): Buyer sought refund of Rs 3 lakh booking amount; HRERA ordered builder to refund it with 10.95% interest.
- RERA-GRG-1071-2023 (complaint, decided 02-Jul-2024): Buyer sought delay compensation and refund; cancellation upheld, builder ordered to refund balance with 10.95% interest.
|
|---|
| Decided cases against ASTER INFRAHOME PVT. LTD. (all its projects) | 72 (Complaint: 63; Compensation: 5; Execution of an earlier order: 4) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026