RERA’d by NeevHQ

Projects · RADHA ESTATES PVT. LTD. ,ORRIS INFRASTRUCTURES PVT. LTD. & THREE C SHELTERS PVT. LTD.

Greenopolis

Radha Estates · Sector 89, Gurugram

Registered with RERA: Jan 2019

Is it legal?

Will it be delivered on time?

Location

The builder: Radha Estates

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameGREENOPOLIS
Builder (promoter)RADHA ESTATES PVT. LTD. ,ORRIS INFRASTRUCTURES PVT. LTD. & THREE C SHELTERS PVT. LTD.
LocationSECTOR-89, MANESAR, GURUGRAM
RERA project IDRERA-GRG-165-2019
Registration certificate numberGGM/311/43/2019/05 DATED 23.01.2019
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2020
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area37.218 acres
Licence115 of 2011 renewed upto 22/12/2019
Estimated cost of the project₹1,19,700 lakh (₹1,197 crore)
Total units (plots, apartments, shops)Not found in the records checked
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-12-2013
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-12-2013
Likely completion date31-12-2020

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusScrutinized: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against RADHA ESTATES PVT. LTD. ,ORRIS INFRASTRUCTURES PVT. LTD. & THREE C SHELTERS PVT. LTD. (all its projects)10 (Complaint: 9; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in