Projects · PAREENA INFRASTRUCTURE PVT LTD

Group Housing Colony (Micasa)

Pareena Infrastructure · Sector 68, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 68; the exact site was not found.

The builder: Pareena Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameGROUP HOUSING COLONY (MICASA)
Builder (promoter)PAREENA INFRASTRUCTURE PVT LTD
LocationSECTOR 68, GURUGRAM
RERA project IDRERA-GRG-558-2020
Registration certificate number99 OF 2017 DATED 28.08.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/12/2025
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area13.48275 acres
Licence. 111 of 2013 dated 27.12.2013, License No. 92 of 2014 dated 13.08.2014 and License No. 94 of 2014 dated 13.08.2014
Estimated cost of the project₹44,469 lakh (₹444.69 crore)
Total units (plots, apartments, shops)1120
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 468–721 sq ft carpet, 616 units; 3 BHK: 831–1,056 sq ft carpet, 234 units; 3 BHK + servant room: 1,241 sq ft carpet, 102 units (source: the builder's registration form (Form A-H))
Units booked when registered425
Units unsold when registered696
Layout plan approved on28-04-2015
Building plans approved on28-04-2015

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-06-2022
Revised completion date12-08-2024
Infrastructure: projected completion12-08-2024
Infrastructure: percentage complete when registered10%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on28-Jul-2026
Quarterly reports listed on the portal31

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹495.91 lakh (₹4.96 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹347.13 lakh (₹3.47 crore)
Project bank account (escrow): withdrawn in the quarter₹424.56 lakh (₹4.25 crore)
Project bank account (escrow): balance at quarter end₹0.61 lakh (₹0.01 crore)
Units in the project (apartments / plots)Not found in the records checked
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹5,832.57 lakh (₹58.33 crore) paid; ₹0 due
Approvals listed
  • Zoning Plan: Obtained Approval 29-10-2014
  • Service Plans: Obtained Approval 20-12-2022
  • Electricity Plans: Obtained Approval 25-04-2022
  • Site Plans: Obtained Approval 28-04-2015
  • Building Plans: Obtained Approval 28-04-2015
  • Fire NOC: Obtained Approval 24-11-2015

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 15 Jul 2026, for 30 Jun 2026
By part
  • Sub structure (Table A): 99.3%
  • Super structure (Table A): 99.3%
  • Mechanical MEP (Table A): 99.3%
  • Electrical MEP (Table A): 99.3%
  • Plumbing and firefighting (Table A): 99.3%
  • Internal finishing (Table A): 99.3%
  • External finishing (Table A): 99.3%
  • Internal roads and pavements: 99%, In progress
  • Parking: 99%, In progress
  • Water supply: 99%, In progress
  • Sewerage: 99%, In progress
  • Storm water drains: 99%, In progress
  • Landscaping and tree plantation: 97%, In progress
  • Parks and playgrounds: 100%, Completed
  • Benches: 0%, Completed
  • Shopping area: 100%, Completed
  • Street lighting and electrification: 99%, In progress
  • Treatment and disposal of sewage and STP: 100%, Completed
  • Water conservation and rain water harvesting: 100%, In progress
  • Energy management (solar): 100%, Completed
  • Fire protection and fire safety: 100%, Completed
  • Electrical meter room, sub-station, receiving station: 100%, Completed
  • Community Centre: 100%, Completed
  • Schools: 50%, In progress
Unclear in the certificate
  • Table A has a blank building or tower name, so its percentages are shown as project-level figures.
  • Benches are shown as 00% complete but the remarks say Completed.
  • The certificate lists floor counts for several towers (34, 22, 22, 34, 35, 25, 26 floors) without tower names, so tower-wise progress cannot be matched to them.
  • Work done during the quarter is not filled in Table A.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project23
Cases
Decided cases against PAREENA INFRASTRUCTURE PVT LTD (all its projects)187 (Complaint: 120; Execution of an earlier order: 21; Compensation: 46)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in