Projects · ST. PATRICKS REALTY PVT.LTD.
Group Housing Colony Of 10.925 Acres
St. Patricks Realty · Sector 32, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Jan 2026 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not file REP-I (Part A to H) on web portal for offline registered project (Jun 2022, open)
- Did not submit its quarterly progress report (May 2022, open)
- Failed to file REP-I project details and quarterly progress reports for Sector 32 project (Nov 2019, open). At stake: Penalty of ₹25,000 per day from 31 Dec 2019; no final amount recorded
- 2 more cases: reply 4
Will it be delivered on time?
- Original deadline Dec 2024, extended to Jan 2026
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Jan 2023) covers: Tower-C only, 52 dwelling units (52 flats)
- Construction, as certified by the architect (Jan–Mar 2026):
- Done: Tower a, Tower b
- Money: ₹558.4 crore spent of ₹505.1 crore (CA certificate, Mar 2026)
What's on offer?
- Registration now covers 766
Location
- Nearest metro: Millennium City Centre Gurugram, 6.7 km by road (24 min by car)
- Cyber City 29 min · Airport 36 min by car at 9:30 am
- Within 3 km: 51 hospitals, 16 schools, 4 malls
Location shown for Sector 32; the exact site was not found.
The builder: St. Patricks Realty
- 11 projects registered in Gurugram
- 2 with an occupation certificate on record
- 57 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GROUP HOUSING COLONY OF 10.925 ACRES |
|---|---|
| Builder (promoter) | ST. PATRICKS REALTY PVT.LTD. |
| Location | SECTOR-32, SOHNA GURUGRAM |
| RERA project ID | RERA-GRG-665-2020 |
| Registration certificate number | 150 OF 2017 DATED 28.08.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/01/2026 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 148.6833 acres |
| Licence | 54 of 2014 (19-06-2024), 28 of 2016 (22-12-2021), 07 of 2020 (28-01-2025) |
| Estimated cost of the project | ₹1,20,233.8 lakh (₹1,202.34 crore) |
| Total units (plots, apartments, shops) | 1149 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 252 |
| Units unsold when registered | 328 |
| Layout plan approved on | 13-12-2019 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-07-2022 |
|---|---|
| Revised completion date | 31-12-2024 |
| Infrastructure: projected completion | 31-12-2024 |
| Infrastructure: percentage complete when registered | 47% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2026 (JAN-MAR) |
| Latest report submitted on | 14-Apr-2026 |
| Quarterly reports listed on the portal | 30 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹114.41 lakh (₹1.14 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹-23.38 lakh (₹-0.23 crore) |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹89.34 lakh (₹0.89 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 766 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹5,718.04 lakh (₹57.18 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 01 Apr 2026, for Mar'26 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against ST. PATRICKS REALTY PVT.LTD. (all its projects) | 57 (Complaint: 50; Execution of an earlier order: 5; Compensation: 2) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in