Group Housing Colony
Ram Avtar Yadav · Sector 67, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jul 2022)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not file REP-I (Part A to H) on web portal for offline registered project (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2023, open)
- Failed to file quarterly progress reports (REP-I Part A to H) online and in hard copy (Nov 2019, open). At stake: Authority decided ₹25,000 per day penalty from 31 Dec 2019 while default continues
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Nov 2025, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
Location
- Nearest metro: Sector 55–56, 8.3 km by road (27 min by car)
- Cyber City 51 min · Airport 60 min by car at 9:30 am
- Within 3 km: 9 hospitals, 18 schools, 3 malls
Location shown for Sector 67; the exact site was not found.
The builder: Ram Avtar Yadav
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GROUP HOUSING COLONY |
|---|---|
| Builder (promoter) | RAM AVTAR YADAV |
| Location | SECTOR 67, GURUGRAM |
| RERA project ID | RERA-GRG-373-2019 |
| Registration certificate number | 161 OF 2017 DATED 29.08.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/07/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.78125 acres |
| Licence | LC 46 of 2008 |
| Estimated cost of the project | Not found in the records checked |
| Total units (plots, apartments, shops) | Not found in the records checked |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 20-12-2020 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 20-12-2020 |
|---|---|
| Likely completion date | 25-11-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2022 (OCT-DEC) |
| Latest report submitted on | 09-Jan-2023 |
| Quarterly reports listed on the portal | 17 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2022 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | Not found in the records checked |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed | Not found in the records checked |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Unclear in the certificate |
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against RAM AVTAR YADAV (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in