Projects · BURMAN GSC ESTATE PVT. LTD
Gurgaon Spectrum Centre (PHASE-1) ( Commercial Project)
Burman Gsc Estate · Sector 82A, Gurugram
Registered with RERA: Sep 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jun 2020)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit a quarterly progress report (May 2022, open)
- Did not apply for registration extension or submit completion, part-completion or occupation certificate, or requisite documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
- 21 complaints about this project decided by HRERA since Nov 2023 (20 delay interest ordered, 1 refund ordered)
Will it be delivered on time?
- Deadline Jun 2020, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Oct–Dec 2024):
- In progress: Building/tower no. 1 - external finishing 99.94%, Building/tower no. 1 - super structure 99.83%, Building/tower no. 1 - sub structure 99.63%, Building/tower no. 1 - mechanical 99.45%, Building/tower no. 1 - compound wall 99%, Building/tower no. 1 - electrical 98.89%, and 12 more
- Money: ₹236.3 crore spent of ₹236.3 crore (CA certificate, Dec 2024)
Location
- Nearest metro: Millennium City Centre Gurugram, 17.5 km by road (47 min by car)
- Cyber City 52 min · Airport 43 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 0 malls
Location shown for Sector 82A; the exact site was not found.
The builder: Burman Gsc Estate
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 27 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | GURGAON SPECTRUM CENTRE (PHASE-1) ( COMMERCIAL PROJECT) |
|---|
| Builder (promoter) | BURMAN GSC ESTATE PVT. LTD |
|---|
| Location | SECTOR- 82A, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-385-2019 |
|---|
| Registration certificate number | 222 OF 2017 DATED 18.09.2017 |
|---|
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/06/2020 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 17957.20 acres |
|---|
| Licence | 135 of 2008(27-06-2020) |
|---|
| Estimated cost of the project | ₹20,779 lakh (₹207.79 crore) |
|---|
| Total units (plots, apartments, shops) | 300 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 92 |
|---|
| Units unsold when registered | 208 |
|---|
| Layout plan approved on | 31-08-2015 |
|---|
| Building plans approved on | 04-11-2015 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2020 |
|---|
| Revised completion date | 30-06-2020 |
|---|
| Infrastructure: projected completion | 30-06-2020 |
|---|
| Infrastructure: percentage complete when registered | 15% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/12/2024 (OCT-DEC) |
|---|
| Latest report submitted on | 25-Feb-2025 |
|---|
| Quarterly reports listed on the portal | 25 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹62.74 lakh (₹0.63 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹250 lakh (₹2.5 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹406.4 lakh (₹4.06 crore) |
|---|
| Spent on infrastructure in the quarter | ₹406.94 lakh (₹4.07 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹7.22 lakh (₹0.07 crore) |
|---|
| Units in the project (apartments / plots) | 246 apartments, 246 plots |
|---|
| Sold in the quarter | 0 apartments, 0 plots |
|---|
| EDC (development charges): paid / due as on date | ₹957.49 lakh (₹9.57 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 06-10-2008
- Zoning Plan: Obtained Approval 25-04-2013
- Service Plans: Obtained Approval 01-07-2013
- Electricity Plans: Obtained Approval 10-02-2016
- Fire NOC: Obtained Approval 12-07-2023
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 02 Jan 2023, for 31 Dec 2022 |
|---|
| By part | - Building/Tower no. 1 - Sub Structure: 99.63%, Excavation, raft and basement levels 1 and 2 at 100%; waterproofing at 99%
- Building/Tower no. 1 - Super Structure: 99.83%, G+18 floors; all slabs completed
- Building/Tower no. 1 - Mechanical (lift, ventilation): 99.45%
- Building/Tower no. 1 - Electrical (conduiting, wiring, fixtures): 98.89%
- Building/Tower no. 1 - Plumbing and firefighting: 79.72%
- Building/Tower no. 1 - Internal finishing: 95.02%
- Building/Tower no. 1 - External finishing: 99.94%
- Building/Tower no. 1 - Lifts installation: 92%, 7 of 8 lifts installed
- Building/Tower no. 1 - Entrance lobby finishing: 40%, Stone cladding and flooring done
- Building/Tower no. 1 - Compound wall: 99%, Finishing done; concertina wire remaining
- Common areas - Internal roads and pavements: 85%
- Common areas - Sewerage (chambers, lines, STP): 98%
- Common areas - Storm water drains: 97%, Storm water line installed on site
- Common areas - Treatment and disposal of sewage/STP: 97%
- Common areas - Fire protection and fire safety: 93%
- Common areas - Landscaping and tree plantation: 80%
- Common areas - Street lighting/electrification: 60%
- Common areas - Water supply: 0%
|
|---|
| Unclear in the certificate | - Table A value columns (work done during quarter and cumulative value) appear misaligned in the text, so rupee figures were not used.
- Table B parking entries (covered and open numbers) are blank.
- Table B entry for parks and playgrounds is garbled; it is marked No.
- Several Table A and Table B sub-item percentages are split across lines, so some stage details may be incomplete.
- Certificate refers to a single Tower/Building no. 1 only; the number of other towers in the phase is not stated.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2816-2022: The case page does not say what the proceeding is about. It lists the parties as HARERA Gurugram (through a representative) and Burman GSC Estate Pvt. Ltd, with the district as Gurugram. Status: The case page shows the status as 'Online complaint not yet received at office'. No next hearing date is listed.
- RERA-GRG-3284-2022: Show cause notice to the promoter, Burman GSC Estate Pvt. Ltd., for not submitting a quarterly progress report. The case is registered as a complaint and the Authority started it. The Authority's show cause notice asks the promoter to appear at a first hearing and give a written reply. Status: First hearing listed for 27 Jun 2022. The listing shows status 'First Hearing' with no proceedings or order recorded yet. Latest: 27 Jun 2022, First hearing was listed before the Authority. No proceedings or bench order are shown in the record.
- RERA-GRG-3329-2022: Show cause notice issued to the promoter for not applying for extension of registration, not submitting completion, part completion or occupation certificate, and not submitting requisite documents. Status: First hearing listed for 28 Jun 2022. No hearing proceedings or order are recorded on the case page. Latest: 28 Jun 2022, First hearing was listed. The case page shows the status as FIRST HEARING, with no proceedings, bench or order recorded.
- RERA-GRG-3331-2022: Show-cause notice to the promoter, BURMAN GSC ESTATE PVT. LTD, for not adhering to the time period it declared for completing the project, under section 4(2)(l)(C). The Authority started this case itself. Status: Listed for first hearing on 30 Jun 2022. The listing shows no proceedings or order for that day yet. Latest: 30 Jun 2022, First hearing listed. Status shown as FIRST HEARING, with no proceedings recorded.
- RERA-GRG-5051-2022: Case listed as HARERA Gurugram through an individual versus Burman GSC Estate Pvt. Ltd. The page does not state what the complaint is about. Status: At the first hearing stage. Hearing was listed for 30 Jun 2022. The page shows no proceedings or order for that hearing. Latest: 16 Jul 2022, Documents received and submitted by the complainant side, recorded as a new complaint.
- RERA-GRG-5526-2019: The Authority started this proceeding against the promoter for not filing REP-I Part A to H on the web portal and not filing Quarterly Progress Reports (QPR) for a project registered offline. The Authority issued notices, including a show cause notice and notices under section 42(1D), and the case concerns compliance with these requirements. Status: Pending. The page lists the next hearing as 17 Feb 2020. The last notice shown was dispatched on 03 Sep 2020, and the page shows no order after that. Latest: 03 Sep 2020, Fourth notice dispatched, a notice for compliance with section 42(1D). Penalty: The promoter was warned that it may be liable for penalty under section 63 if the filings were not made. The page shows no penalty imposed.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 21 |
|---|
| Cases | - RERA-GRG-2762-2025 (complaint, decided 25-Aug-2026): Buyer sought delay interest and conveyance deed; builder ordered to pay 10.80% interest and execute deed in 60 days.
- RERA-GRG-3051-2025 (complaint, decided 19-Feb-2026): Buyers sought fresh account after delay adjustment; Authority ordered 10.80% delayed possession interest, conveyance deed in 60 days.
- RERA-GRG-915-2025 (complaint, decided 13-Feb-2026): Buyers sought delay interest and GST relief; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-3329-2025 (complaint, decided 30-Jan-2026): Buyer sought delayed possession charges for late serviced apartment; builder ordered to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3021-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3015-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-4122-2025 (complaint, decided 16-Dec-2025): Buyer sought delay compensation for a commercial unit; builder ordered to pay 10.80% delay interest and execute conveyance deed.
- RERA-GRG-4340-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3009-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3032-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3008-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3148-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3033-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3207-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-2999-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3020-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3837-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3312-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3278-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-3149-2025 (complaint, decided 16-Dec-2025): Buyers sought delayed possession interest and disclosures; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-4303-2023 (complaint, decided 10-Jan-2025): Buyer sought refund after possession delay at The Spectrum; builder ordered to refund paid amount with 11.10% interest.
|
|---|
| Decided cases against BURMAN GSC ESTATE PVT. LTD (all its projects) | 27 (Complaint: 26; Execution of an earlier order: 1) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in