Habitat Prime

Prime Infradevelopers · Sector 99A, Gurugram

Registered with RERA: Jun 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Prime Infradevelopers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameHABITAT PRIME
Builder (promoter)PRIME INFRADEVELOPERS PVT LTD
LocationVILLAGE DHANKOT, SEC-99A, GUR UGRAM
RERA project IDRERA-GRG-806-2021
Registration certificate numberGGM/458/190/2021/26 DATED 22.06.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to24/11/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area6.46875 acres
Licence38 of 2020 dated 26.11.2020
Estimated cost of the project₹19,266.28 lakh (₹192.66 crore)
Total units (plots, apartments, shops)844
Unit sizes (carpet area, as declared)844 units averaging about 630 sq ft carpet (8 towers)
Flat types (BHK), as stated by the builder2 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on24-02-2021
Building plans approved on24-02-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2021
Likely completion date24-11-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal21

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹2.47 lakh (₹0.02 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹14,443.96 lakh (₹144.44 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1,538.06 lakh (₹15.38 crore)
Project bank account (escrow): deposited in the quarter₹27.46 lakh (₹0.27 crore)
Project bank account (escrow): withdrawn in the quarter₹23.68 lakh (₹0.24 crore)
Project bank account (escrow): balance at quarter end₹6.37 lakh (₹0.06 crore)
Units in the project (apartments / plots)844 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹757.04 lakh (₹7.57 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 16-10-2020
  • Zoning Plan: Obtained Approval 26-11-2020
  • Service Plans: Obtained Approval 14-06-2021
  • Site Plans: Obtained Approval 24-02-2021
  • Building Plans: Obtained Approval 24-02-2021
  • Fire NOC: Obtained Approval 02-06-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 29 Sep 2026, for 30 Sep 2026
By part
  • Tower A-7: 100%, All listed Table A activities certified at 100%, including finishing, lifts, fire pump and compound wall
  • Tower A-1: 100%, All listed Table A activities certified at 100%, including finishing, lifts, fire pump and compound wall
  • Tower A-6: 100%, All listed Table A activities certified at 100%, including finishing, lifts, fire pump and compound wall
  • Tower A-2: 100%, All listed Table A activities certified at 100%, including finishing, lifts, fire pump and compound wall
  • Tower A-4: 100%, Table A items certified at 100% up to lifts installation and overhead tanks; later items are cut off in the copy
Unclear in the certificate
  • Table B (overall percentage by activity for the entire project) is not in the copy provided.
  • Table A is shown only for Towers A-7, A-1, A-6, A-2 and A-4. Towers A-3, A-5 and A-8 are not covered in the copy.
  • For Tower A-4, Table A items 16 (ix) onwards and items 17 to 19 are not visible in the copy.
  • The certificate gives no single overall percentage of construction completed or work done in the quarter.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against PRIME INFRADEVELOPERS PVT LTD (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in