Projects · SUPERTECH LTD.

Hill Crest/Officer Enclave(Low Rise Floor)

Supertech · Sector 02, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Supertech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameHILL CREST/OFFICER ENCLAVE(LOW RISE FLOOR)
Builder (promoter)SUPERTECH LTD.
LocationSECTOR -02, GURUGRAM
RERA project IDRERA-GRG-551-2020
Registration certificate number258 OF 2017 DATED 03.10.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to02/10/2020
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area18.37 acres
Licence124 of 2014 dated 23/08/2014
Estimated cost of the project₹44,523.66 lakh (₹445.24 crore)
Total units (plots, apartments, shops)708
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder3 BHK: 708 units (source: the builder's registration form (Form A-H))
Units booked when registered0
Units unsold when registered0
Layout plan approved on23-08-2014
Building plans approved on22-04-2015

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion dateNot found in the records checked
Revised completion dateNot found in the records checked
Infrastructure: projected completion02-10-2020
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2023 (OCT-DEC)
Latest report submitted on03-Jul-2024
Quarterly reports listed on the portal21

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹385.33 lakh (₹3.85 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹73.54 lakh (₹0.74 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹22.16 lakh (₹0.22 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)744 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹8.11 lakh (₹0.08 crore) paid; ₹6,350.89 lakh (₹63.51 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 06-01-2023
  • Zoning Plan: Obtained Approval 18-12-2014
  • Service Plans: Obtained Approval 19-02-2024
  • Site Plans: Obtained Approval 12-01-2015
  • Building Plans: Obtained Approval 17-02-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 02 Jul 2024, for 31 Dec 2023
By part
  • HILL CREST - Sub structure (excavation, foundation, basements, waterproofing): 74.15%
  • HILL CREST - Super structure (slabs, brick work, block work, staircase, lift wells, water tank): 45.74%
  • HILL CREST - MEP Mechanical (lifts, ventilation): 24.07%
  • HILL CREST - MEP Electrical (conduiting, wiring, fixtures): 19.26%
  • HILL CREST - MEP Plumbing & Firefighting (piping, pumps, pump room, fixtures): 40.93%
  • HILL CREST - Finishing Internal (plaster, tiling, flooring, painting within units and common areas): 25.36%
  • HILL CREST - Finishing External (plaster, painting, facade): 31.3%
  • HILL CREST - Stilt floor / ground floor: 72.22%
  • HILL CREST - Status of laying of slabs (cumulative, tower): 57.78%
  • HILL CREST - Fixing of door and window frames in flats: 24.07%
  • HILL CREST - Waterproofing of terraces: 14.44%
  • HILL CREST - Entrance lobby finishing: 19.26%
  • HILL CREST - Compound wall: 24.07%
  • Common services - Internal roads and pavements: 52.96%
  • Common services - Parking: 57.78%
  • Common services - Water supply, sewerage and storm water drains: 77.04%
  • Common services - Landscaping and tree plantation: 28.89%
  • Common services - Street lighting / electrification: 96.3%
  • Common services - Fire protection and fire safety: 24.07%
  • Common services - Water conservation and rain water harvesting: 19.26%
  • Common services - Shopping area, STP, solid waste management, electrical meter room, underground water tank, schools, dispensary, creche, nursery school, taxi stand, milk and vegetable booth, nursing home, commercial building: 0%
Unclear in the certificate
  • Table A is headed as 'Building/ tower no. HILL CREST' while the project is described as a component of HILLTOWN; the tower-wise split is not clear.
  • The certificate gives component-wise percentages only, not one overall figure for the project.
  • Total floors entry reads '744 Units' and carpet area is given as '100,399.08 Sq. Mtr'; the floor count is not clearly stated.
  • Note 2 says physical progress was calculated on estimated construction cost and cost incurred, and covers several earlier quarters.
  • Site inspection date is 16 Jun 2024, while the certificate is dated 02 Jul 2024.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; Pending: 2; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SUPERTECH LTD. (all its projects)317 (Complaint: 248; Compensation: 49; Execution of an earlier order: 20)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in