Hill Estate

Supertech · Sector 2, Gurugram

Registered with RERA: Jan 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 2; the exact site was not found.

The builder: Supertech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameHILL ESTATE
Builder (promoter)SUPERTECH LIMITED
LocationSECTOR-2, SOHNA
RERA project IDRERA-GRG-784-2020
Registration certificate numberGGM/433/165/2021/01 DATED 08.01.2021
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to30/11/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area8.59166 acres
Licence39 OF 2020
Estimated cost of the project₹6,515.29 lakh (₹65.15 crore)
Total units (plots, apartments, shops)184
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on10-12-2020
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-04-2021
Likely completion date30-11-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2023 (OCT-DEC)
Latest report submitted on09-Aug-2024
Quarterly reports listed on the portal11

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)184 plots
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹601.29 lakh (₹6.01 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 10-12-2020
  • Demarcation Plan: Obtained Approval 10-12-2020
  • Zoning Plan: Obtained Approval 19-02-2021
  • Service Plans: Obtained Approval 26-11-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 02 Aug 2024, for 31 Dec 2023
By part
  • Hill Estate - Sub structure (excavation, foundation, basements, waterproofing): 80%
  • Hill Estate - Super structure (slabs, brick work, staircase, lift wells, water tank): 100%
  • Hill Estate - MEP Mechanical (lifts, ventilation): 0%
  • Hill Estate - MEP Electrical (conduiting, wiring, fixtures): 0%
  • Hill Estate - MEP Plumbing and Firefighting (piping, pumps, fixtures): 75%
  • Hill Estate - Finishing internal (plaster, tiling, flooring, painting): 100%
  • Hill Estate - Finishing external (plaster, painting, facade): 100%
  • Internal roads and pavements: 100%
  • Parking: Not proposed
  • Water supply: 95%
  • Sewerage (chamber, lines, septic tanks): 95%
  • Storm water drains: 95%
  • Landscaping and tree plantation: 95%
  • Parks and playgrounds: 96%
  • Fixing of children play equipment: 100%
  • Benches: 90%
  • Shopping area: 0%
  • Street lighting and electrification: 100%
  • Treatment and disposal of sewage and sullage water / STP: 95%
  • Solid waste management and disposal: Not proposed
  • Water conservation, rain water harvesting, percolating: 100%
  • Energy management (solar): Not proposed
  • Fire protection and fire safety requirements: Not proposed
  • Electrical meter room, sub-station, receiving station: 40%
  • Underground water tank: Not proposed
  • Compound wall: Not proposed
  • Community centre (to be transferred to RWA): 0%
  • Commercial building: 0%
Unclear in the certificate
  • Table A gives sub-structure as 80.00% complete, but the task list shows excavation at 95.00% and raft foundation at 0.00%. The certificate does not explain the difference.
  • The certificate says the physical progress was calculated from estimated and incurred construction costs, and it covers several past quarters (2018 to 2024). The quarter-only progress is not separately stated.
  • The certificate lists the total floors as 184 Units, which may be a data entry error. The unit is not clear.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed3
By statusFirst Hearing: 3
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SUPERTECH LIMITED (all its projects)317 (Complaint: 248; Compensation: 49; Execution of an earlier order: 20)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in