Projects · EXPERION DEVELOPERS PRIVATE LIMITED

Hub 108

Experion Developers · Sector 108, Gurugram

Registered with RERA: Oct 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Experion Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameHUB 108
Builder (promoter)EXPERION DEVELOPERS PRIVATE LIMITED
LocationSECTOR 108, GURUGRAM, HARYANA
RERA project IDRERA-GRG-1154-2022
Registration certificate numberGGM/615/347/2022/90 DATED 03.10.2022
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to05/05/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.15 acres
Licence57 of 2013 dated 11.07.2013 , 114 of 2019 dated 12.09.2019
Estimated cost of the project₹1,192.09 lakh (₹11.92 crore)
Total units (plots, apartments, shops)18
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on18-04-2022
Building plans approved on18-04-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-03-2023
Likely completion date05-05-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on13-Oct-2026
Quarterly reports listed on the portal15

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)18 plots
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹472.83 lakh (₹4.73 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 05-11-2015
  • Demarcation Plan: Obtained Approval 30-09-2015
  • Zoning Plan: Obtained Approval 27-04-2017
  • Service Plans: Obtained Approval 18-04-2022
  • Electricity Plans: Obtained Approval 18-04-2022

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 07 Oct 2026, for 30 Sep 2026
By part
  • Sub structure: 0%
  • Super structure: 0%
  • MEP - Mechanical: 0%
  • MEP - Electrical: 0%
  • MEP - Plumbing and firefighting: 0%
  • Finishing - Internal: 0%
  • Finishing - External: 0%
  • Other, including external development cost, horticulture, parks, streetlight or PHE, water supply, sewerage: 100%, Cumulative work done value 340.39 lacs
  • Compliance to conditions of approval: 100%, Yes, applicable for entire project
Unclear in the certificate
  • The report period is shown as 30th September 2026 with 07th Oct 2026 in brackets; the meaning of the bracketed date is not stated.
  • The certificate gives no single overall percentage of construction complete or of work done in the quarter.
  • Table A lists the area as 1.15 Acres (18 Residential Plots) with no separate tower or block names, and the floor-area row shows 1.15 Acre against 0.00%.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusFirst Hearing: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EXPERION DEVELOPERS PRIVATE LIMITED (all its projects)74 (Complaint: 60; Compensation: 9; Execution of an earlier order: 5)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in