RERA’d by NeevHQ

Projects · SUPERTECH LIMITED

Hues Towers And Azalia Towers

Supertech · Sector 68, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Supertech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameHUES TOWERS AND AZALIA TOWERS
Builder (promoter)SUPERTECH LIMITED
LocationVILLAGE BADSHAHPUR, SECTOR 68 , GURUGRAM
RERA project IDRERA-GRG-450-2019
Registration certificate number182 OF 2017 DATED 04.09.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2021
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area32.83 acres
Licence106,89,134,and 136
Estimated cost of the project₹1,67,437.27 lakh (₹1,674.37 crore)
Total units (plots, apartments, shops)2856
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder1 BHK: 334 sq ft carpet, 624 units; 2 BHK: 568–625 sq ft carpet, 1,472 units; 2 BHK + study: 803 sq ft carpet, 448 units; 3 BHK: 730–973 sq ft carpet, 312 units (source: the builder's registration form (Form A-H))
Units booked when registered1559
Units unsold when registered1297
Layout plan approved on02-02-2017
Building plans approved on02-02-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2021
Revised completion date30-06-2022
Infrastructure: projected completion31-12-2021
Infrastructure: percentage complete when registered5%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2023 (OCT-DEC)
Latest report submitted on30-Jun-2024
Quarterly reports listed on the portal21

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹522.92 lakh (₹5.23 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹123.99 lakh (₹1.24 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹212.74 lakh (₹2.13 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)3179 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹3,417.27 lakh (₹34.17 crore) paid; ₹10,975.12 lakh (₹109.75 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 20-05-2015
  • Zoning Plan: Obtained Approval 26-05-2015
  • Site Plans: Obtained Approval 26-05-2015
  • Building Plans: Obtained Approval 02-02-2017
  • Fire NOC: Obtained Approval 19-04-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 11 Jun 2024, for 31st December 2023
By part
  • Tower-A: 91.61%, Super structure; G+24 floors
  • Tower-B: 91.61%, Super structure; G+24 floors
  • Tower-C: 0%, Super structure; G+24 floors
  • Tower-D: 0%, Super structure; G+24 floors
  • Tower-E: 91.61%, Super structure; G+24 floors
  • Tower-F: 91.61%, Super structure; G+24 floors
  • Tower-G: 62.68%, Super structure; G+24 floors
  • Tower-H: 62.68%, Super structure; G+24 floors
  • Tower-K: 11.57%, Super structure; G+28 floors
  • Tower-T: 11.57%, Super structure; G+28 floors
  • Tower-M: 60.18%, Super structure; G+28 floors
  • Tower-N: 60.18%, Super structure; G+28 floors
  • Tower-V: 7.71%, Super structure; G+28 floors
  • Tower-W: 9.64%, Super structure; G+28 floors
  • Tower-O: 19.94%, Super structure; G+28 floors
  • Tower-P: 14.46%, Super structure; G+28 floors
  • T-1: 21.68%, Super structure; G+26 floors
  • T-2: 5.35%, Super structure; G+26 floors
  • T-3: 0%, Super structure; G+26 floors
  • T-4: 0%, Super structure; G+11 floors
  • T-5: 14.61%, Super structure; G+24 floors
  • T-6: 6.75%, Super structure; G+24 floors
  • T-7: 0%, Super structure; G+12 floors
  • Comm. Shops: 65.57%, Super structure; 1 floor
Unclear in the certificate
  • The certificate gives no single overall percent complete figure. Gross figures are given for each activity (for example, Gross super structure 14.07% and Gross sub structure 8.14%).
  • The by_part figures are the total floors (super structure) percentages for each tower. Other activities (sub structure, MEP, finishing) are given separately for each tower in the certificate and are not included here.
  • The certificate states a site inspection date of 17.5.2024 and a certification date of 11.6.2024, and says the figures are based on company books and estimated cost, not on a physical measure of work.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusFirst Hearing: 3; Online Complaint Not Yet Received At Office: 1; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project64
Cases
Decided cases against SUPERTECH LIMITED (all its projects)317 (Complaint: 248; Compensation: 49; Execution of an earlier order: 20)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in