Projects · ILD MILLENNIUM PVT. LTD
ILD Grand Centra ( Tower 1)
ILD Millennium · Sector 37C, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Feb 2020)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not apply to extend expired registration; did not submit completion or occupation certificate (Jun 2022, open)
- Did not complete the project within the completion time it declared (Jun 2022, open)
- Did not submit its quarterly progress report (May 2022, open)
- 3 more cases: reply 4
- 7 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 1 refund ordered, 3 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Apr 2023, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK: 68 units
- 3 BHK: 136 units
- 4 BHK: 12 units
Location
- Nearest metro: Millennium City Centre Gurugram, 14.6 km by road (47 min by car)
- Cyber City 53 min · Airport 38 min by car at 9:30 am
- Within 3 km: 13 hospitals, 6 schools, 1 mall
The builder: ILD Millennium
- 2 projects registered in Gurugram, 1 lapsed
- 1 with an occupation certificate on record
- 95 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ILD GRAND CENTRA ( TOWER 1) |
|---|---|
| Builder (promoter) | ILD MILLENNIUM PVT. LTD |
| Location | SECTOR- 37C, GURUGRAM |
| RERA project ID | RERA-GRG-557-2020 |
| Registration certificate number | 62 OF 2017 DATED 17.8.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 16/02/2020 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 3.6372 acres |
| Licence | LICENCE NO. 13 OF 2008 |
| Estimated cost of the project | ₹11,319 lakh (₹113.19 crore) |
| Total units (plots, apartments, shops) | 216 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK: 68 units; 3 BHK: 136 units; 4 BHK: 12 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 67 |
| Units unsold when registered | 137 |
| Layout plan approved on | 31-01-2008 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-04-2020 |
|---|---|
| Revised completion date | 30-04-2023 |
| Infrastructure: projected completion | 30-04-2023 |
| Infrastructure: percentage complete when registered | 15% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in