Projects · IMPERIA WISHFIELD PRIVATE LIMITED
Imperia Shopping Central
Imperia Wishfield · Sector 37, Gurugram
Registered with RERA: Jul 2022
Is it legal?
- RERA registered, valid till Mar 2025 (date has passed)
- HRERA has opened 2 cases of its own against the builder over this project (2 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- Did not get architectural control sheet approved within two months; approved 144 days late (Nov 2022, open). At stake: Proposed forfeiture of security and revocation of registration certificate; no penalty imposed yet
Will it be delivered on time?
- Original deadline Mar 2024, extended to Mar 2025
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Sep 2024) covers: Commercial plotted colony, 2.825 acres, Sector-37-C Gurugram (no flats listed)
- Construction, as certified by the architect (Jan–Mar 2025):
- Done: Internal roads & pavements, Parking, Sewerage, Storm water drains, Water conservation, rain water harvesting, percolating well / pit
- In progress: 36 nos commercial plot – mechanical common area 95%, Parks and playgrounds 95%, 36 nos commercial plot – finishing, external 90%, Landscaping & tree plantation 90%, 36 nos commercial plot – electrical 80%, 36 nos commercial plot – finishing, internal 80%, and 11 more
- Money: ₹50.1 crore spent of ₹60.1 crore; ₹10 crore still to spend (CA certificate, Mar 2025)
What's on offer?
- 36 plots, 97–172 sq yd
The builder: Imperia Wishfield
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 175 buyer complaints decided by HRERA
Full details and sources are below.
Registration
| Project name | IMPERIA SHOPPING CENTRAL |
|---|---|
| Builder (promoter) | IMPERIA WISHFIELD PRIVATE LIMITED |
| Location | VILLAGE GADOLI KHURD, SECTOR- 37, GURUGRAM |
| RERA project ID | RERA-GRG-1009-2022 |
| Registration certificate number | GGM/587/319/2022/62 DATED 11.07.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/03/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 2.825 acres |
| Licence | 117 OF 2021 |
| Estimated cost of the project | ₹5,538.76 lakh (₹55.39 crore) |
| Total units (plots, apartments, shops) | 36 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 23-12-2021 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2022 |
|---|---|
| Likely completion date | 31-03-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2025 (JAN-MAR) |
| Latest report submitted on | 03-May-2025 |
| Quarterly reports listed on the portal | 10 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹234.26 lakh (₹2.34 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹24.14 lakh (₹0.24 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹57.12 lakh (₹0.57 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹1.83 lakh (₹0.02 crore) |
| Units in the project (apartments / plots) | 36 plots |
| Sold in the quarter | 10 plots |
| EDC (development charges): paid / due as on date | ₹663.23 lakh (₹6.63 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 02 Apr 2025, for 01 Jan 2025 – 31 Mar 2025 |
|---|---|
| By part |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against IMPERIA WISHFIELD PRIVATE LIMITED (all its projects) | 175 (Complaint: 137; Execution of an earlier order: 23; Compensation: 15) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in