Independent Floors At DLF City Phase I

DLF Real Estate Builders · DLF City Phase – I, Gurugram

Registered with RERA: Mar 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for the area; the exact site was not found.

The builder: DLF Real Estate Builders

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameINDEPENDENT FLOORS AT DLF CITY PHASE I
Builder (promoter)DLF REAL ESTATE BUILDERS LIMITED
LocationDLF CITY PHASE - I
RERA project IDRERA-GRG-840-2021
Registration certificate numberGGM/448/180/2021/16 DATED 25.03.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/02/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.621 acres
Licence-
Estimated cost of the project₹5,253.23 lakh (₹52.53 crore)
Total units (plots, apartments, shops)28
Unit sizes (carpet area, as declared)4 units of 1,457 sq ft carpet (1 tower); 8 units of 1,667 sq ft carpet; 4 units of 2,218 sq ft carpet (1 tower); 12 units of 2,371 sq ft carpet
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on23-03-2021
Building plans approved on23-03-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction14-05-2021
Likely completion date28-02-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2024 (APR-JUN)
Latest report submitted on12-Jul-2024
Quarterly reports listed on the portal13

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2024 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹2.78 lakh (₹0.03 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹2,794.7 lakh (₹27.95 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,299.4 lakh (₹12.99 crore)
Project bank account (escrow): deposited in the quarter₹94.4 lakh (₹0.94 crore)
Project bank account (escrow): withdrawn in the quarter₹1,056 lakh (₹10.56 crore)
Project bank account (escrow): balance at quarter end₹5,389.39 lakh (₹53.89 crore)
Units in the project (apartments / plots)28 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Zoning Plan: Obtained Approval 26-10-2016
  • Site Plans: Obtained Approval 19-03-2021
  • Building Plans: Obtained Approval 19-03-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 09 Jul 2024, for 30 Jun 2024
By part
  • Towers F-13/2, F-13/3, F-13/4, F-13/5, F-13/6, F-16/5 and F-3/1A (Table A, listed together): Table A component progress: sub structure 100%, super structure 100%, mechanical 100%, electrical 42%, plumbing and firefighting 74%, internal finishing 88%, external finishing 64%. Detailed status sheet shows most internal and external works completed; fixing of door and window frames and firefighting fittings are marked TBS.
Unclear in the certificate
  • The certificate gives no single overall percentage. Table A lists several towers together, so no separate figure is given for each tower.
  • The certificate refers to Table B, but no Table B is in the document. The status sheet has no percentage totals.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusFirst Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DLF REAL ESTATE BUILDERS LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026