Independent Floors At DLF City Phase II

DLF Projects · DLF City Phase II, Gurugram

Registered with RERA: Jul 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for the area; the exact site was not found.

The builder: DLF Projects

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameINDEPENDENT FLOORS AT DLF CITY PHASE II
Builder (promoter)DLF PROJECTS LIMITED
LocationDLF CITY PHASE II
RERA project IDRERA-GRG-866-2021
Registration certificate numberGGM/461/193/2021/29 DATED 06.07.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.963 acres
LicenceNA
Estimated cost of the project₹17,089.33 lakh (₹170.89 crore)
Total units (plots, apartments, shops)52
Unit sizes (carpet area, as declared)4 units of 1,356 sq ft carpet (1 tower); 8 units of 1,420 sq ft carpet; 4 units of 1,456 sq ft carpet (1 tower); 4 units of 1,466 sq ft carpet (1 tower); 4 units of 1,474 sq ft carpet (1 tower); 4 units of 1,527 sq ft carpet (1 tower); 4 units of 1,687 sq ft carpet (1 tower); 4 units of 1,691 sq ft carpet (1 tower); 16 units of 1,777 sq ft carpet
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on19-07-2018
Building plans approved on18-06-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction14-09-2021
Likely completion date30-06-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2024 (APR-JUN)
Latest report submitted on12-Jul-2024
Quarterly reports listed on the portal11

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2024 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹997.15 lakh (₹9.97 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹4,353.61 lakh (₹43.54 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹2,608.37 lakh (₹26.08 crore)
Project bank account (escrow): deposited in the quarter₹823.59 lakh (₹8.24 crore)
Project bank account (escrow): withdrawn in the quarter₹1,600 lakh (₹16 crore)
Project bank account (escrow): balance at quarter end₹7,158.53 lakh (₹71.59 crore)
Units in the project (apartments / plots)48 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 26-10-2016
  • Zoning Plan: Obtained Approval 26-10-2016
  • Building Plans: Obtained Approval 16-06-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 09 Jul 2024, for 30 Jun 2024
By part
  • Sub structure (excavation, foundation, basements, water proofing): 100%
  • Super structure (slabs, brick work, block work, stair case, lift wells, machine rooms, water tank): 89%
  • MEP - Mechanical (lifts, ventilation): 100%
  • MEP - Electrical (conduiting, wiring, fixtures): 60%
  • MEP - Plumbing & Firefighting (piping, pumps and pump room, fixtures): 51%
  • Finishing - Internal (plaster, tiling, flooring, painting within units and common areas): 86%
  • Finishing - External (plaster, painting, facade): 40%
Unclear in the certificate
  • Table A lists 13 building/tower numbers together in one table, not separately for each tower as the certificate's own instructions require. It is not clear which percentages apply to which tower.
  • The certificate refers to Table B, but Table B is not in the document.
  • Table A shows work done during the quarter for some items (for example, 20, 62, 13 and 12 lacs) and 0 for others, but no overall quarterly percentage is stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DLF PROJECTS LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026