Independent Floors At DLF City Phase IV
DLF · Sector 27, Gurugram
Registered with RERA: Mar 2022
Is it legal?
- RERA registered, valid till May 2025 (date has passed)
- HRERA opened a case of its own against the builder in Aug 2025 (still open):
- Why: did not complete Independent Floors project at DLF City Phase IV within declared time; registration expired
- Latest: order uploaded to case record 19 Sep 2025; next hearing 01 Oct 2025
Will it be delivered on time?
- Deadline May 2025, never extended (date has passed)
- Occupation certificate (Dec 2023) covers: Residential building on plot 5043, DLF City Phase IV (4 flats)
- Construction, as certified by the architect (Jan–Mar 2024):
- Done: Towers 5029 to 5043
- In progress: Super structure 78%, Mechanical 75%, Internal finishing 68%, Plumbing and firefighting 55%, External finishing 45%, Electrical 33%
- Money: ₹62.9 crore spent of ₹94.7 crore; ₹31.8 crore still to spend (CA certificate, Mar 2024)
What's on offer?
- 60 units: 60 sold, 0 unsold (builder's certificate, Mar 2024)
- Independent Floors: 60 of 60 sold
- 60 units in 6 sizes, as declared to HRERA:
- 16 units of 1,399 sq ft carpet (4 towers)
- 4 units of 1,550 sq ft carpet (1 tower)
- 8 units of 1,585 sq ft carpet (2 towers)
- 12 units of 1,640 sq ft carpet (3 towers)
- 8 units of 1,669 sq ft carpet (2 towers)
- 12 units of 1,906 sq ft carpet (3 towers)
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
- 15 plots, 276–411 sq yd
Location
- Nearest metro: Sector 42-43, 3.8 km by road (12 min by car)
- Cyber City 15 min · Airport 33 min by car at 9:30 am
- Within 3 km: 20 hospitals, 21 schools, 18 malls
The builder: DLF
- 14 projects registered in Gurugram
- 6 with an occupation certificate on record
- 18 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | INDEPENDENT FLOORS AT DLF CITY PHASE IV |
|---|---|
| Builder (promoter) | DLF LIMITED |
| Location | DLF CITY PHASE IV, SECTOR-27, GURUGRAM, HARYANA |
| RERA project ID | RERA-GRG-1001-2022 |
| Registration certificate number | GGM/539/271/2022/14 DATED 14.03.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 15/05/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 1.625 acres |
| Licence | 208 of 2008 (25.12.2008) |
| Estimated cost of the project | ₹9,549.16 lakh (₹95.49 crore) |
| Total units (plots, apartments, shops) | 75 |
| Unit sizes (carpet area, as declared) | 16 units of 1,399 sq ft carpet (4 towers); 4 units of 1,550 sq ft carpet (1 tower); 8 units of 1,585 sq ft carpet (2 towers); 12 units of 1,640 sq ft carpet (3 towers); 8 units of 1,669 sq ft carpet (2 towers); 12 units of 1,906 sq ft carpet (3 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 10-01-2022 |
| Building plans approved on | 26-01-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 16-05-2022 |
|---|---|
| Likely completion date | 15-05-2025 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2024 (JAN-MAR) |
| Latest report submitted on | 13-Apr-2024 |
| Quarterly reports listed on the portal | 8 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2024 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹4,439.28 lakh (₹44.39 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹5,122.18 lakh (₹51.22 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹1,170.18 lakh (₹11.7 crore) |
| Project bank account (escrow): deposited in the quarter | ₹3,556.07 lakh (₹35.56 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹992 lakh (₹9.92 crore) |
| Project bank account (escrow): balance at quarter end | ₹15,216.04 lakh (₹152.16 crore) |
| Units in the project (apartments / plots) | 60 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 09 Apr 2024, for 31 Mar 2024 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against DLF LIMITED (all its projects) | 18 (Complaint: 15; Compensation: 3) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in