RERA’d by NeevHQ

Projects · DLF HOME DEVELOPERS LIMITED

Independent Floors At DLF City Phase IV

DLF Home Developers · DLF City Phase IV, Gurugram

Registered with RERA: Sep 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for the area; the exact site was not found.

The builder: DLF Home Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameINDEPENDENT FLOORS AT DLF CITY PHASE IV
Builder (promoter)DLF HOME DEVELOPERS LIMITED
LocationDLF CITY PHASE IV, GURUGRAM, HARYANA
RERA project IDRERA-GRG-897-2021
Registration certificate numberGGM/483/215/2021/51 DATED 14.09.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to14/11/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.8314 acres
LicenceSince the development of the Independent Floors is being undertaken on Plot basis, in a licensed Colony, all the conditions of Policy of Independent Floors in State of Haryana as amended from time to
Estimated cost of the project₹10,163.91 lakh (₹101.64 crore)
Total units (plots, apartments, shops)44
Unit sizes (carpet area, as declared)4 units of 1,354 sq ft carpet (1 tower); 8 units of 1,463 sq ft carpet; 4 units of 1,545 sq ft carpet (1 tower); 12 units of 1,548 sq ft carpet; 4 units of 1,646 sq ft carpet (1 tower); 4 units of 1,686 sq ft carpet (1 tower); 4 units of 1,688 sq ft carpet (1 tower); 4 units of 2,019 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on30-04-2008
Building plans approved on10-09-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction15-11-2021
Likely completion date14-11-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2024 (OCT-DEC)
Latest report submitted on11-Jan-2025
Quarterly reports listed on the portal13

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,150.93 lakh (₹11.51 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹5,045.62 lakh (₹50.46 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,816.28 lakh (₹18.16 crore)
Project bank account (escrow): deposited in the quarter₹806.54 lakh (₹8.07 crore)
Project bank account (escrow): withdrawn in the quarter₹134 lakh (₹1.34 crore)
Project bank account (escrow): balance at quarter end₹6,370.35 lakh (₹63.7 crore)
Units in the project (apartments / plots)44 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 26-10-2016
  • Zoning Plan: Obtained Approval 26-10-2016
  • Site Plans: Obtained Approval 31-08-2021
  • Building Plans: Obtained Approval 31-08-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 06 Jan 2025, for 31 Dec 2024
By part
  • Sub structure (all towers listed in Table A): 100%, Excavation and basement level 1 completed
  • Super structure (all towers listed in Table A): 99%, Slab laying in progress; 66 slabs laid by end of quarter
  • Mechanical MEP (all towers listed in Table A): 100%
  • Electrical MEP (all towers listed in Table A): 96%
  • Plumbing and firefighting (all towers listed in Table A): 83%
  • Internal finishing (all towers listed in Table A): 93%
  • External finishing (all towers listed in Table A): 85%
Unclear in the certificate
  • Table A lists towers 4813, 4814, 4815, 4816, 3613, 3615, 3617, 3619, 1031, 6118 and 9001 together in one table, so progress is not given separately for each tower.
  • The certificate refers to Table B, but no Table B appears in the document.
  • Some items are marked TBS (to be submitted), including electrical fittings within flats, firefighting fittings as per CFO NOC, and electrical fittings in common areas; no percentage is given for these.
  • No single overall percentage of construction completion is stated in the document.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DLF HOME DEVELOPERS LIMITED (all its projects)25 (Complaint: 21; Compensation: 3; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in