The builder: DLF Luxury Homes

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameINDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
Builder (promoter)DLF LUXURY HOMES LIMITED
LocationDLF GARDEN CITY, SECTOR 91 / 92,
RERA project IDRERA-GRG-817-2021
Registration certificate numberGGM/444/176/2021/12 DATED 22.03.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to20/06/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area0.986 acres
Licence-
Estimated cost of the project₹7,305.27 lakh (₹73.05 crore)
Total units (plots, apartments, shops)64
Unit sizes (carpet area, as declared)20 units of 1,422 sq ft carpet; 44 units of 1,563 sq ft carpet
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on19-02-2019
Building plans approved on11-02-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-06-2021
Likely completion date20-06-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2024 (JUL-SEP)
Latest report submitted on12-Oct-2024
Quarterly reports listed on the portal14

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2024 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹422.47 lakh (₹4.22 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹4,180.14 lakh (₹41.8 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,936.94 lakh (₹19.37 crore)
Project bank account (escrow): deposited in the quarter₹320.69 lakh (₹3.21 crore)
Project bank account (escrow): withdrawn in the quarter₹800 lakh (₹8 crore)
Project bank account (escrow): balance at quarter end₹81.02 lakh (₹0.81 crore)
Units in the project (apartments / plots)64 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 28-10-2014
  • Zoning Plan: Obtained Approval 29-08-2017
  • Service Plans: Obtained Approval 25-02-2021
  • Electricity Plans: Obtained Approval 25-02-2021
  • Building Plans: Obtained Approval 21-12-2020
  • Fire NOC: Obtained Approval 21-12-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Oct 2024, for 30 Sep 2024
By part
  • Towers G1-14, G1-16, G1-17, G1-18, G1-19, G1-20, NA-95, NA-96, NA-97, NA-98, NA-99, G11-2, G11-3, G11-4, G11-5, G11-6: 100%, All listed sub-structure, super-structure, MEP and finishing items certified at 100% of proposed work; no work value recorded for the quarter
Unclear in the certificate
  • Table B is referred to in the certificate but is not included in the document, so per-tower figures beyond the Table A listing cannot be confirmed.
  • Table A lists all towers in one combined table, and no overall single percentage is stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusFirst Hearing: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DLF LUXURY HOMES LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026