India Rashtra

Next Generation Projects · Sector 88A, Gurugram

Registered with RERA: Nov 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Next Generation Projects

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameINDIA RASHTRA
Builder (promoter)NEXT GENERATION PROJECTS PVT LTD
LocationSECTOR 88A
RERA project IDRERA-GRG-1174-2022
Registration certificate numberGGM/631/363/2022/106 DATED 21.11.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/11/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area10.01875 acres
Licence144 OF 2022 DATED 28-09-2022
Estimated cost of the project₹32,286 lakh (₹322.86 crore)
Total units (plots, apartments, shops)78
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on28-09-2022
Building plans approved on30-11-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2022
Likely completion date30-11-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2025 (OCT-DEC)
Latest report submitted on15-Jan-2026
Quarterly reports listed on the portal12

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹5.63 lakh (₹0.06 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹2,053.07 lakh (₹20.53 crore)
Other costs in the quarter (EDC, taxes, etc.)₹6,011.69 lakh (₹60.12 crore)
Project bank account (escrow): deposited in the quarter₹5.63 lakh (₹0.06 crore)
Project bank account (escrow): withdrawn in the quarter₹5.63 lakh (₹0.06 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)79 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹1,887.21 lakh (₹18.87 crore) paid; ₹549.58 lakh (₹5.5 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 28-09-2022
  • Demarcation Plan: Obtained Approval 28-10-2022
  • Zoning Plan: Obtained Approval 10-04-2024
  • Service Plans: Obtained Approval 14-08-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Jan 2025, for 31 Dec 2025
By part
  • Internal roads & pavements: 95%
  • Parking: 0%
  • Water supply: 95%
  • Sewerage (chamber, lines, septic tank, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation: 25%
  • Parks and playgrounds: 15%
  • Fixing of children play equipment: 0%
  • Benches: 0%
  • Shopping Area: 0%
  • Street Lighting/Electrification: 100%
  • Treatment and disposal of sewage and sullage water/STP: 65%
  • Solid Waste Management & disposal: 0%
  • Water Conservation, Rain Water Harvesting, Percolating Well/Pit: 100%
  • Energy management (Solar): not stated
  • Fire Protection and Fire Safety Requirements: 0%
  • Electrical meter room, Sub-Station, Receiving station: 0%
  • Community centre: 23%
  • Schools: 0%
  • Dispensary: not stated
  • Club: not stated
  • Services/facilities to be transferred to the Competent Authority: 0%
Unclear in the certificate
  • Table A (tower/building-wise construction status) is marked NA for every item, so no tower-wise progress is reported.
  • The quarter is stated as ending 31 Dec 2025, but the certificate and site inspection dates are 05 Jan 2025 and 03 Jan 2025. The year may be a typo.
  • Table B does not state an overall percentage for the whole project.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against NEXT GENERATION PROJECTS PVT LTD (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026