Projects · CITRA PROPERTIES LTD.
Indiabulls One 09, PHASE-1
Citra Properties · Sector 109, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till May 2025 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Part A to H) on the Authority's web portal for an offline-registered project (Jun 2022, open)
- Did not submit quarterly progress report (May 2022, open)
- Did not submit completion, part completion or occupation certificate after registration extension lapsed (Jun 2022, open)
- 4 more cases: reply 4
- 9 complaints about this project decided by HRERA since Nov 2023 (8 delay interest ordered, 1 refund ordered)
Will it be delivered on time?
- Original deadline May 2023, extended 2 times to May 2025
- Occupation certificate (Jul 2024) covers: Blocks 1 and 2 plus basements, Sector 109
- Construction, as certified by the architect (Jul–Sep 2024):
- Money: ₹142.4 crore spent of ₹142.4 crore (CA certificate, Sep 2024)
What's on offer?
- Registration now covers 128
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 7 km by road (11 min by car)
- Cyber City 50 min · Airport 29 min by car at 9:30 am
- Within 3 km: 6 hospitals, 1 school, 1 mall
The builder: Citra Properties
- 2 projects registered in Gurugram
- 2 with an occupation certificate on record
- 22 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | INDIABULLS ONE 09, PHASE-1 |
|---|
| Builder (promoter) | CITRA PROPERTIES LTD. |
|---|
| Location | SECTOR-109, VILLAGE PAWALA KH USRUPUR, GURGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-1613-2024 |
|---|
| Registration certificate number | 333 OF 2017 DATED 24.10.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 04/05/2025 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 3.216 acres |
|---|
| Licence | 43 of 2012 dated 05.05.2012 |
|---|
| Estimated cost of the project | ₹14,242.04 lakh (₹142.42 crore) |
|---|
| Total units (plots, apartments, shops) | 137 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 127 |
|---|
| Units unsold when registered | 10 |
|---|
| Layout plan approved on | 17-10-2019 |
|---|
| Building plans approved on | 17-10-2019 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 02-10-2021 |
|---|
| Revised completion date | 04-05-2023 |
|---|
| Infrastructure: projected completion | 04-05-2023 |
|---|
| Infrastructure: percentage complete when registered | 100% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2024 (JUL-SEP) |
|---|
| Latest report submitted on | 15-Oct-2024 |
|---|
| Quarterly reports listed on the portal | 24 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2024 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹60.39 lakh (₹0.6 crore) |
|---|
| Units in the project (apartments / plots) | 128 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹637.73 lakh (₹6.38 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 10-10-2011
- Demarcation Plan: Obtained Approval 10-10-2011
- Zoning Plan: Obtained Approval 07-05-2012
- Service Plans: Obtained Approval 25-03-2021
- Electricity Plans: Obtained Approval 08-09-2015
- Site Plans: Obtained Approval 03-10-2018
- Building Plans: Obtained Approval 03-10-2018
- Fire NOC: Obtained Approval 07-07-2021
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 07 Oct 2024, for September 2024 |
|---|
| By part | - Tower 1B: 100%, Sub-structure and super-structure marked completed; MEP and finishing items marked 100%; compound wall 100%
- Tower 1C: 100%, Sub-structure and super-structure items shown at 100%; MEP and finishing items shown at 100%
|
|---|
| Unclear in the certificate | - Project is listed as Towers 1B, 1C, 2A, 2B and 2C, but the certificate has tables only for Towers 1B and 1C.
- For Tower 1B, some installation and finishing lines (firefighting fittings, electrical fittings in common areas, environmental NOC compliance, terrace waterproofing, entrance lobby finishing) are left blank.
- The Tower 1C table continues onto a page where the status list is cut off, so later items are not visible.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | - Extension of registration certificate (Form REP-V, conditions of extension no. 05 of 2019) for IndiaBulls One09 Phase-1 project, Sector-109, Gurugram: The registration of the IndiaBulls One09 Phase-1 project is extended by one year and is now valid till 30 Apr 2020. The project is a commercial project in Sector-109, Village Pawala Khusrupur, Gurugram, with a registered project area of 3.216 acres and a total licensed area of 5.90 acres. It has 5 towers, 121 apartments and 3 screens, and the promoter is Citra Properties Limited. The extension is subject to conditions: the promoter must submit the occupation certificate when received, offer to execute and register conveyance deeds in favour of allottees, deposit seventy percent of amounts realized from allottees in a separate schedule bank account to cover construction and land cost, and comply with the Act, its rules and regulations, and other applicable laws. If the conditions are not met, the Authority may take action, including revoking the registration.
|
|---|
| Extensions of registration | |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | First Hearing: 4; Online Complaint Not Yet Received At Office: 2; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2617-2022: Non-filing of REP-I (Part A to H) on the Authority's web portal for a project registered offline with the Interim Real Estate Regulatory Authority, Panchkula or HRERA Gurugram. The case is listed in the name of HARERA Gurugram against Citra Properties Ltd. Status: Listed at First Hearing. Next date of hearing is 29 Jun 2022. The page shows no order or proceedings for that hearing yet. Latest: 29 Jun 2022, First hearing scheduled. The case page lists the status as First Hearing, with no proceedings, bench order or order upload recorded.
- RERA-GRG-3005-2022: The case page is titled as a complaint by HARERA Gurugram through a named representative against Citra Properties Ltd. The page does not state what the complaint is about. Status: The page shows the complaint as an online complaint not yet received at the office. It has not been dispatched. No next hearing date is set. No hearing or order is listed.
- RERA-GRG-3506-2022: Show cause notice to the promoter, Citra Properties Ltd, for not submitting a quarterly progress report Status: First hearing listed for 27 Jun 2022. The page shows no proceedings or order for that hearing. Latest: 27 Jun 2022, First hearing listed. The status shows FIRST HEARING. No proceedings, bench order or order upload is recorded on the page.
- RERA-GRG-3886-2022: The Authority started this proceeding against CITRA Properties Ltd because the completion, part completion or occupation certificate was not submitted after the validity of the registration extension lapsed. The page also lists submission of the requisite documents. Status: First hearing listed for 11 Jul 2022. The page records no proceedings of the day and no order uploaded. Latest: 11 Jul 2022, First hearing listed. The status shows FIRST HEARING, with no proceedings or order recorded.
- RERA-GRG-3889-2022: A proceeding listed under case number RERA-GRG-3889-2022 between HARERA Gurugram (through its officer) and CITRA Properties Ltd. The page does not state the reason for the case. Status: The page shows the status as 'Online complaint not yet received at office'. No next hearing date is listed, and the complaint dispatch fields show 'NA' or 'Not Yet'.
- RERA-GRG-5114-2022: Complaint filed against Citra Properties Ltd, a real estate company, before the Haryana Real Estate Regulatory Authority, Gurugram. The complaint is recorded under case number RERA-GRG-5114-2022. The page does not state the reason for the complaint. Status: At first hearing stage. The page lists the first hearing on 30 Jun 2022 with status 'First Hearing'. No order is shown. Latest: 16 Jul 2022, A document was received and submitted by the complainant under Dak ID 37969, marked as 'New Complaint'.
- RERA-GRG-5472-2019: The Authority's own case against promoter CITRA Properties Ltd for not filing project updates (REP-I Part A to H and quarterly progress reports) on the web portal, with a show cause notice on possible revocation of registration. Status: Pending. The next hearing was fixed for 24 Feb 2020 at 3:00 pm as a final opportunity for personal hearing. The page also shows a fourth notice dispatched on 16 Jul 2020, with no later order recorded. Latest: 16 Jul 2020, Fourth notice dispatched under Section 42(1D) (tracking ID EH770719725IN). Penalty: The Authority decided to impose a penalty of Rs 25,000 per day from 31 Dec 2019, the deadline for online filing of REP-I (Part A to H), while the default continues. The penalty may add up to five percent of the estimated cost of the real estate project, as determined by the Authority.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 9 |
|---|
| Cases | - RERA-GRG-2949-2025 (complaint, decided 17-Jul-2026): Buyers of a delayed shop; builder ordered to pay 10.80% interest, hand over possession, and execute conveyance deed.
- RERA-GRG-2950-2025 (complaint, decided 13-Feb-2026): Buyers sought delay relief; builder ordered to pay 10.80% interest, hand over the shop, and execute conveyance deed.
- RERA-GRG-5831-2024 (complaint, decided 20-Jan-2026): Shop cancelled by builder after delayed possession; HRERA set aside cancellation, ordered reinstatement and 10.80% delay interest.
- RERA-GRG-1772-2025 (complaint, decided 13-Jan-2026): Buyers sought delay interest and conveyance deed; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-1773-2025 (complaint, decided 13-Jan-2026): Buyers sought delay interest and conveyance deed; HRERA ordered builder to pay 10.80% interest and execute conveyance deed.
- RERA-GRG-6133-2024 (complaint, decided 23-Dec-2025): Buyers sought possession and delay interest on a shop; HRERA ordered possession within 30 days and 10.80% interest from 09 May 2021.
- RERA-GRG-5045-2024 (complaint, decided 10-Dec-2025): Buyers of a shop challenged cancellation after delay; HRERA set aside cancellation, ordered reinstatement and 10.85% delay interest.
- RERA-GRG-859-2024 (complaint, decided 16-Jul-2025): Buyers sought delay interest and possession of a shop; HRERA ordered builder to pay 11.10% interest from 04 Oct 2021 and hand over the shop.
- RERA-GRG-1905-2022 (complaint, decided 08-Nov-2024): Buyer sought refund after possession delay; builder ordered to refund amount paid with 11.10% interest.
|
|---|
| Decided cases against CITRA PROPERTIES LTD. (all its projects) | 22 (Complaint: 20; Compensation: 2) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in