Projects · SPAZE TOWERS PVT. LTD
Ishan Singh ( Commercial)
Spaze Towers · Sector 78, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Dec 2025)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit the quarterly progress report, prompting a show-cause notice (May 2022, open)
- Did not apply to extend registration, submit completion or occupation certificate, or required documents (Jun 2022, open)
- Did not complete the project within the time it declared (Jun 2022, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Original deadline Jun 2020, extended to Dec 2025
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Oct–Dec 2023):
- In progress: Arrow - sub structure 91.85%, Arrow - super structure 74.01%, Common services: other internal development work 42%, Common services: internal roads & pavements 30%, Common services: water supply, sewerage, storm, stp & rain water harvesting 25%, Common services: construction of circulation road 22%, and 6 more
- Money: ₹68.8 crore spent of ₹136.7 crore; ₹68 crore still to spend (CA certificate, Dec 2023)
What's on offer?
- 486 units: 187 sold, 299 unsold (builder's certificate, Dec 2023)
- Registration now covers 486
Location
- Nearest metro: Millennium City Centre Gurugram, 21.5 km by road (52 min by car)
- Cyber City 59 min · Airport 49 min by car at 9:30 am
- Within 3 km: 1 hospital, 0 schools, 0 malls
Location shown for Sector 78; the exact site was not found.
The builder: Spaze Towers
- 6 projects registered in Gurugram, 1 lapsed
- 5 with an occupation certificate on record
- 208 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ISHAN SINGH ( COMMERCIAL) |
|---|---|
| Builder (promoter) | SPAZE TOWERS PVT. LTD |
| Location | SECTOR-78, VILLAGE- NAURANGPU R |
| RERA project ID | RERA-GRG-528-2019 |
| Registration certificate number | 13 OF 2018 DATED 11.01.2018 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2025 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 3.24722 acres |
| Licence | 56 of 2012 date 06.06.2012 |
| Estimated cost of the project | ₹13,674.31 lakh (₹136.74 crore) |
| Total units (plots, apartments, shops) | 479 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 397 |
| Units unsold when registered | 82 |
| Layout plan approved on | 28-02-2013 |
| Building plans approved on | 10-09-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2020 |
|---|---|
| Revised completion date | 30-06-2020 |
| Infrastructure: projected completion | 30-06-2020 |
| Infrastructure: percentage complete when registered | 45% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2023 (OCT-DEC) |
| Latest report submitted on | 19-Feb-2024 |
| Quarterly reports listed on the portal | 21 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹6.35 lakh (₹0.06 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0.48 lakh (₹0 crore) |
| Units in the project (apartments / plots) | 486 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹890.86 lakh (₹8.91 crore) paid; ₹1,309.3 lakh (₹13.09 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Dec 2023, for 31 Dec 2023 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SPAZE TOWERS PVT. LTD (all its projects) | 208 (Complaint: 184; Execution of an earlier order: 14; Compensation: 10) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026