IT Colony ( Commerce Park)
Emaar MGF Land · Sector 61, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Sep 2031
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not apply to extend registration or submit completion, part completion or occupation certificate (Jun 2022, open)
- Did not complete the project within the time it declared (Jun 2022, open)
- Did not submit quarterly progress report (open)
- 3 more cases: reply 4
Will it be delivered on time?
- Original deadline Mar 2021, extended to Sep 2031
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction 0% complete (architect, Jul–Sep 2026)
- Money: ₹253.5 crore spent of ₹1,368.7 crore; ₹1,115.2 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 374 units: 247 sold, 127 unsold (builder's certificate, Sep 2026)
- Registration now covers 297
Location
- Nearest metro: Sector 55–56, 2.9 km by road (10 min by car)
- Cyber City 34 min · Airport 51 min by car at 9:30 am
- Within 3 km: 6 hospitals, 7 schools, 1 mall
Location shown for Sector 61; the exact site was not found.
The builder: Emaar MGF Land
- 22 projects registered in Gurugram, 1 lapsed
- 19 with an occupation certificate on record
- 1,022 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | IT COLONY ( COMMERCE PARK) |
|---|---|
| Builder (promoter) | EMAAR MGF LAND LTD |
| Location | SECTOR- 61, GHATA, GURUGRAM |
| RERA project ID | RERA-GRG-670-2020 |
| Registration certificate number | 58 OF 2017 DATED 17.08.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/09/2031 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 5.65 acres |
| Licence | 34 of 2008 |
| Estimated cost of the project | Not found in the records checked |
| Total units (plots, apartments, shops) | 0 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 0 |
| Units unsold when registered | 0 |
| Layout plan approved on | 17-08-2017 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-03-2021 |
|---|---|
| Revised completion date | 31-03-2021 |
| Infrastructure: projected completion | 31-03-2021 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 12-Oct-2026 |
| Quarterly reports listed on the portal | 32 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹9,426 lakh (₹94.26 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹10,429 lakh (₹104.29 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹13,775 lakh (₹137.75 crore) |
| Project bank account (escrow): deposited in the quarter | ₹6,598.33 lakh (₹65.98 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹7,287.75 lakh (₹72.88 crore) |
| Project bank account (escrow): balance at quarter end | ₹1,039.64 lakh (₹10.4 crore) |
| Units in the project (apartments / plots) | 374 apartments, 374 plots |
| Sold in the quarter | 93 apartments, 93 plots |
| EDC (development charges): paid / due as on date | ₹3,531.54 lakh (₹35.32 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 08 Oct 2026, for Sept 26 |
|---|---|
| Overall work complete | 0% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against EMAAR MGF LAND LTD (all its projects) | 1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400 |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in