Projects · JMS INFRA REALITY PVT. LTD.
Jms Group Capital Square
Jms Infra Reality · Sector 95, Gurugram
Registered with RERA: Aug 2024
Is it legal?
- RERA registered, valid till Mar 2028
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Mar 2028, never extended
- No occupation certificate yet (not ready for possession)
- Construction 42.91% complete (architect, Jul–Sep 2026)
- Money: ₹37.6 crore spent of ₹51.5 crore; ₹13.9 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 236 units in 33 sizes, as declared to HRERA:
- 36 units of 129 sq ft carpet
- 21 units of 155 sq ft carpet
- 34 units of 161 sq ft carpet
- 20 units of 200 sq ft carpet
- 17 units of 203 sq ft carpet
- 42 units of 219 sq ft carpet
- 27 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 24.6 km by road (59 min by car)
- Cyber City 62 min · Airport 43 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
Location shown for Sector 95; the exact site was not found.
The builder: Jms Infra Reality
- 8 projects registered in Gurugram
- 2 with an occupation certificate on record
- 2 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | JMS GROUP CAPITAL SQUARE |
|---|---|
| Builder (promoter) | JMS INFRA REALITY PVT. LTD. |
| Location | SECTOR 95, VILLAGE-WAZIRPUR |
| RERA project ID | RERA-GRG-1626-2024 |
| Registration certificate number | GGM/855/587/2024/82 DATED 02.08.2024 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/03/2028 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 0.85 acres |
| Licence | 11 of 2022 dated 02.02.2022, license no 4 of 2023 dated 06.01.2023, license no 111 of 2023 dated 25.05.2023 |
| Estimated cost of the project | ₹4,105.92 lakh (₹41.06 crore) |
| Total units (plots, apartments, shops) | 236 |
| Unit sizes (carpet area, as declared) | 2 units of 103 sq ft carpet; 2 units of 121 sq ft carpet; 36 units of 129 sq ft carpet; 2 units of 131 sq ft carpet; 4 units of 141 sq ft carpet; 2 units of 150 sq ft carpet; 2 units of 151 sq ft carpet; 21 units of 155 sq ft carpet; 1 unit of 157 sq ft carpet; 2 units of 160 sq ft carpet; 34 units of 161 sq ft carpet; 2 units of 164 sq ft carpet; 2 units of 169 sq ft carpet; 7 units of 178 sq ft carpet; 1 unit of 187 sq ft carpet; 1 unit of 197 sq ft carpet; 20 units of 200 sq ft carpet; 17 units of 203 sq ft carpet; 2 units of 210 sq ft carpet; 6 units of 214 sq ft carpet; 2 units of 216 sq ft carpet; 42 units of 219 sq ft carpet; 1 unit of 232 sq ft carpet; 5 units of 234 sq ft carpet; 1 unit of 238 sq ft carpet; 1 unit of 239 sq ft carpet; 1 unit of 241 sq ft carpet; 5 units of 242 sq ft carpet; 7 units of 245 sq ft carpet; 1 unit of 263 sq ft carpet; 1 unit of 281 sq ft carpet; 1 unit of 327 sq ft carpet; 2 units of 386 sq ft carpet |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 26-05-2023 |
| Building plans approved on | 06-06-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-07-2024 |
|---|---|
| Likely completion date | 31-03-2028 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 23-Oct-2026 |
| Quarterly reports listed on the portal | 8 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹498.81 lakh (₹4.99 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹-224.57 lakh (₹-2.25 crore) |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹174.73 lakh (₹1.75 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹88.06 lakh (₹0.88 crore) |
| Project bank account (escrow): deposited in the quarter | ₹349.17 lakh (₹3.49 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹362.91 lakh (₹3.63 crore) |
| Project bank account (escrow): balance at quarter end | ₹5.13 lakh (₹0.05 crore) |
| Units in the project (apartments / plots) | 238 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹325.13 lakh (₹3.25 crore) paid; ₹89.95 lakh (₹0.9 crore) due |
| Approvals listed | Not found in the records checked |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 05 Oct 2026, for 30 Sep 2026 |
|---|---|
| Overall work complete | 42.91% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against JMS INFRA REALITY PVT. LTD. (all its projects) | 2 (Complaint: 2) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in