Projects · JOYVILLE SHAPOORJI HOUSING PVT. LTD.
Joyville Gurugram Phase III
Joyville Shapoorji Housing · Sector 102, Gurugram
Registered with RERA: May 2019
Is it legal?
- RERA registered, valid till Apr 2024 (date has passed)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit a quarterly progress report (open)
- Did not adhere to the project completion period it declared (Aug 2025, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Apr 2024, never extended (date has passed)
- Occupation certificate (Mar 2024) covers: Towers 10 and 11, EWS floors 8-13, part basement (385 flats)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Club house/ community centre 58%, Play grounds and parks, construction of circulation road 37%, Super structure 36%, Schools 36%, Internal finishing 26%, Other internal development works 25%, and 9 more
- Money: ₹161.8 crore spent of ₹178.5 crore; ₹16.7 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 235 units, as declared to HRERA:
- 235 units averaging about 730 sq ft carpet (2 towers)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: IFFCO Chowk, 14.6 km by road (46 min by car)
- Cyber City 55 min · Airport 35 min by car at 9:30 am
- Within 3 km: 4 hospitals, 2 schools, 1 mall
The builder: Joyville Shapoorji Housing
- 6 projects registered in Gurugram
- 6 with an occupation certificate on record
- 1 buyer complaint decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | JOYVILLE GURUGRAM PHASE III |
|---|---|
| Builder (promoter) | JOYVILLE SHAPOORJI HOUSING PVT. LTD. |
| Location | SECTOR-102, GURUGRAM |
| RERA project ID | RERA-GRG-211-2019 |
| Registration certificate number | GGM/335/67/2019/29 DATED 24.05.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/04/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 1 acres |
| Licence | 14/2018 |
| Estimated cost of the project | ₹17,852 lakh (₹178.52 crore) |
| Total units (plots, apartments, shops) | 235 |
| Unit sizes (carpet area, as declared) | 235 units averaging about 730 sq ft carpet (2 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 12-11-2018 |
| Building plans approved on | 12-11-2018 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-07-2019 |
|---|---|
| Likely completion date | 30-04-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 29 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0.38 lakh (₹0 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 235 apartments |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹1,362 lakh (₹13.62 crore) paid; ₹6 lakh (₹0.06 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against JOYVILLE SHAPOORJI HOUSING PVT. LTD. (all its projects) | 1 (Complaint: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in