Kashi

Jai Ganga Realtech · Sector 89 & 93, Gurugram

Registered with RERA: Aug 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Jai Ganga Realtech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameKASHI
Builder (promoter)JAI GANGA REALTECH LLP
LocationVILLAGE BADHA AND HAYATPUR, SECTOR 89 & 93
RERA project IDRERA-GRG-2013-2025
Registration certificate numberGGM/977/709/2025/80 DATED 27.08.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to11/01/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.00 acres
Licence7 OF 2022 DATED 19.01.2022
Estimated cost of the project₹14,208.03 lakh (₹142.08 crore)
Total units (plots, apartments, shops)70
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on19-06-2025
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-05-2025
Likely completion date11-01-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on04-Nov-2026
Quarterly reports listed on the portal4

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)69 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Service Plans: Obtained Approval 04-09-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Oct 2026
Overall work complete0%
By part
  • 69 Residential plots and 1 Commercial block: not stated
  • Internal roads & pavements: 0%
  • Water supply: 0%
  • Sewerage (chamber, lines, septic tanks, STP): 0%
  • Storm water drains: 0%
  • Landscaping & tree plantation: 0%
  • Parks and playgrounds: 0%
  • Shopping area: 0%
  • Street lighting/ electrification: 0%
  • Treatment and disposal of sewage and sullage water/ STP: 0%
  • Solid waste management & disposal: 0%
  • Water conservation, rain water harvesting, percolating well/ pit: 0%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Electrical meter room, sub-station, receiving station: 0%
Unclear in the certificate
  • The certificate does not name a quarter. Progress is stated as at 30 Sep 2026.
  • Table A marks every construction activity (sub-structure, super-structure, MEP, finishing) as NA, with no percentage given.
  • Annexure A gives overall structure progress as 00% and pending development as 00%.
  • Work done during the quarter is not stated as a figure.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against JAI GANGA REALTECH LLP (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026