RERA’d by NeevHQ

Projects · KRISUMI CORPORATION PVT. LTD.

Krisumi City Phase 7 (Community Buildings)

Krisumi Corporation · Sector 36A, Gurugram

Registered with RERA: Jun 2026

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Krisumi Corporation

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameKRISUMI CITY PHASE 7 (COMMUNITY BUILDINGS)
Builder (promoter)KRISUMI CORPORATION PVT. LTD.
LocationSECTOR- 36A
RERA project IDRERA-GRG-2204-2026
Registration certificate numberGGM/1066/798/2026/38 DATED 22.06.2026
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/03/2036
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.8499 acres
Licence39 of 2013 dated 4.6.2013, 85 of2014 dated 08.08.2014 , 166 of 2023 dated 18.08.2023 and 71 of 2024 dated 28.06.2024
Estimated cost of the project₹42,876.53 lakh (₹428.77 crore)
Total units (plots, apartments, shops)5
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on13-02-2024
Building plans approved on13-02-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-04-2026
Likely completion date31-03-2036

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal1

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹4,770.25 lakh (₹47.7 crore)
Spent on construction of apartments in the quarter₹4,092 lakh (₹40.92 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹678.25 lakh (₹6.78 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)Not found in the records checked
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 03-05-2013
  • Zoning Plan: Obtained Approval 18-08-2023
  • Service Plans: Obtained Approval 30-07-2024
  • Electricity Plans: Obtained Approval 01-08-2025
  • Site Plans: Obtained Approval 13-02-2024
  • Building Plans: Obtained Approval 13-02-2024
  • Fire NOC: Obtained Approval 02-04-2024

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 01 Oct 2026, for 30 Sep 2026
By part
  • Community Buildings: Sub-structure shown as 42.49% of total proposed work. Excavation 80%, raft foundation 80%, basement level 1 100%, basement level 2 25%, basement level 3 0%. Walls on floors 5%, staircase 6%. Superstructure, MEP and finishing shown as nil.
  • Common areas and facilities (Table B): All listed services and facilities show nil work done.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against KRISUMI CORPORATION PVT. LTD. (all its projects)10 (Complaint: 2; Compensation: 8)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in