Projects · KRRISH REALTECH PVT. LTD
Krrish World
Krrish Realtech · Village Maidawas & Ullawas, Gurugram
Registered with RERA: Oct 2019
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Oct 2019)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit quarterly progress report (Jun 2022, open)
- 3 more cases: reply 4
Will it be delivered on time?
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
Location
- Nearest metro: Sector 55–56, 4.3 km by road (17 min by car)
- Cyber City 41 min · Airport 58 min by car at 9:30 am
- Within 3 km: 5 hospitals, 14 schools, 5 malls
The builder: Krrish Realtech
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 8 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | KRRISH WORLD |
|---|---|
| Builder (promoter) | KRRISH REALTECH PVT. LTD |
| Location | VILLAGE MAIDAWAS & ULLAWAS |
| RERA project ID | RERA-GRG-221-2019 |
| Registration certificate number | GGM/371/103/2019/65 DATED 22.10.2019 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 22/10/2019 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 141.66875 acres |
| Licence | 64 of 2010 dated 20.08.2010 |
| Estimated cost of the project | ₹44,940.26 lakh (₹449.4 crore) |
| Total units (plots, apartments, shops) | 466 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 466 |
| Units unsold when registered | 0 |
| Layout plan approved on | 07-07-2017 |
| Building plans approved on | 07-07-2017 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|---|
| Revised completion date | Not found in the records checked |
| Infrastructure: projected completion | 31-12-2022 |
| Infrastructure: percentage complete when registered | 15% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against KRRISH REALTECH PVT. LTD (all its projects) | 8 (Complaint: 7; Execution of an earlier order: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in