Projects · SECTOR -113,GATEVIDA DEVELOPERS PVT.LTD.

La Vida

Sector -113 · Sector 112, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Sector 113 Gatevida Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameLA VIDA
Builder (promoter)SECTOR -113,GATEVIDA DEVELOPERS PVT.LTD.
LocationVILLAGE BAJGHERA SECTOR-112/1 13,GURUGRAM
RERA project IDRERA-GRG-326-2019
Registration certificate number148 OF 2017 DATED 28.08.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5.989 acres
Licence105 of 2011
Estimated cost of the project₹30,659 lakh (₹306.59 crore)
Total units (plots, apartments, shops)397
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 273 units; 2 BHK + study: 66 units; 3 BHK: 58 units (source: the builder's registration form (Form A-H))
Units booked when registered165
Units unsold when registered232
Layout plan approved on03-06-2016
Building plans approved on03-06-2016

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2022
Revised completion date31-12-2022
Infrastructure: projected completion31-12-2022
Infrastructure: percentage complete when registered2%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on22-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹91 lakh (₹0.91 crore)
Project bank account (escrow): withdrawn in the quarter₹57.04 lakh (₹0.57 crore)
Project bank account (escrow): balance at quarter end₹34.47 lakh (₹0.34 crore)
Units in the project (apartments / plots)397 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹1,539.35 lakh (₹15.39 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 03-06-2016
  • Demarcation Plan: Obtained Approval 24-12-2013
  • Zoning Plan: Obtained Approval 03-06-2016
  • Service Plans: Obtained Approval 24-10-2013
  • Electricity Plans: Obtained Approval 20-06-2013
  • Site Plans: Obtained Approval 30-08-2013
  • Building Plans: Obtained Approval 28-11-2016
  • Fire NOC: Obtained Approval 28-06-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 12 Oct 2026, for Sep 2026
By part
  • Tower B1: Sub structure 100%. Super structure 100% (13 floors, 14 slabs laid). MEP 99.50%. Internal finishing 99.50%. External finishing shown without a percentage. Compliance to environment/CRZ NOC 0%. No work was done in the quarter.
  • Tower B2: Sub structure 100%. MEP 99.90%. Internal finishing 99.50%. No work was done in the quarter. External finishing shown without a percentage.
Unclear in the certificate
  • The certificate gives no single overall percentage for either tower, only component percentages.
  • The MEP percentage for each tower is shown as one figure across the mechanical, electrical and plumbing rows.
  • Detailed status tables are provided only for Tower B1. Tower B2 has only the summary Table A.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against SECTOR -113,GATEVIDA DEVELOPERS PVT.LTD. (all its projects)13 (Complaint: 13)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in