RERA’d by NeevHQ

Projects · LANDMARK APARTMENTS PRIVATE LIMITED

Landmark Avana

Landmark Apartments · Sector 95, Gurugram

Registered with RERA: Feb 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Landmark Apartments

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameLANDMARK AVANA
Builder (promoter)LANDMARK APARTMENTS PRIVATE LIMITED
LocationSECTOR 95, GURUGRAM
RERA project IDRERA-GRG-1244-2022
Registration certificate numberGGM/695/427/2023/39 DATED 13.02.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to29/01/2028
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area14.209 acres
Licence14 OF 2023 DATED 30.01.2023
Estimated cost of the project₹14,284.88 lakh (₹142.85 crore)
Total units (plots, apartments, shops)246
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on01-02-2023
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction30-06-2023
Likely completion date29-01-2028

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2026 (JAN-MAR)
Latest report submitted on23-Jun-2026
Quarterly reports listed on the portal12

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹892.06 lakh (₹8.92 crore)
Borrowed from banks / financial institutions in the quarter₹-422.5 lakh (₹-4.23 crore)
Put in by the builder in the quarter₹-341.47 lakh (₹-3.41 crore)
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹100.96 lakh (₹1.01 crore)
Other costs in the quarter (EDC, taxes, etc.)₹67.17 lakh (₹0.67 crore)
Project bank account (escrow): deposited in the quarter₹624.44 lakh (₹6.24 crore)
Project bank account (escrow): withdrawn in the quarter₹631.26 lakh (₹6.31 crore)
Project bank account (escrow): balance at quarter end₹0.08 lakh (₹0 crore)
Units in the project (apartments / plots)246 plots
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹1,533.97 lakh (₹15.34 crore) paid; ₹1,697.88 lakh (₹16.98 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 01-02-2023
  • Demarcation Plan: Obtained Approval 06-02-2023
  • Zoning Plan: Obtained Approval 22-03-2023
  • Service Plans: Obtained Approval 21-07-2023
  • Electricity Plans: Obtained Approval 09-05-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 07 Apr 2026, for 31 Mar 2026
Overall work complete45.75%
By part
  • Internal roads & pavements: 47%
  • Parking: not stated
  • Water supply: 29%
  • Sewerage (chamber, lines, septic tanks, STP): 42%
  • Storm water drains: 43%
  • Landscaping & tree plantation: 0%
  • Parks and playgrounds: 0%
  • Fixing of children play equipment: 0%
  • Benches: 0%
  • Shopping area: 0%
  • Street lighting/ electrification: 0%
  • Treatment and disposal of sewage and sullage water/ STP: 31.5%
  • Solid waste management & disposal: not stated
  • Water conservation, rain water harvesting, percolating well/ pit: 0%
  • Energy management (solar): not stated
  • Fire protection and fire safety requirements: not stated
  • Electrical meter room, sub-station, receiving station: 0%
  • Compound wall: 20%
  • Soil filling (park and roads): 59%
  • Entrance gate: 0%
  • Approach road to site (24 meters): 90%
  • Tow wall: 95%
  • Parking (sale office): 100%
  • Sale office: 100%
  • Community centre: 0%
Unclear in the certificate
  • The item 'TOW WALL' is written in the certificate as shown; it may be a typing error and its exact meaning is not certain.
  • Table B lists 'Community centre' under community buildings to be transferred to RWA with a percentage shown as '00'. The 'Others' entry under B-2 is blank.
  • Table B does not list any tower or block wise progress; the certificate gives only infrastructure items.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against LANDMARK APARTMENTS PRIVATE LIMITED (all its projects)91 (Complaint: 75; Execution of an earlier order: 8; Compensation: 8)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in