Projects · SRV AUTOMOTIVES PVT. LTD.
Landmark The Homes 81
Srv Automotives · Sector 81, Gurugram
Registered with RERA: Jul 2021
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Feb 2026)
- HRERA has opened 2 cases of its own against the builder over this project (2 open):
- Did not submit quarterly progress report (May 2022, open)
- 1 more case: reply 4
- 12 complaints about this project decided by HRERA since Nov 2023 (6 delay interest ordered, 4 refund ordered, 1 other order, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Feb 2026, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Construction 97.5% complete (architect, Oct–Dec 2025)
- Money: ₹158.9 crore spent of ₹167.3 crore; ₹8.4 crore still to spend (CA certificate, Dec 2025)
What's on offer?
- 780 units in 21 sizes, as declared to HRERA:
- 12 units of 76 sq ft carpet
- 36 units of 194 sq ft carpet (3 towers)
- 45 units of 348 sq ft carpet (8 towers)
- 112 units of 560 sq ft carpet (8 towers)
- 80 units of 567 sq ft carpet (8 towers)
- 448 units of 645 sq ft carpet
- 15 less common sizes: see the full list below
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 21.6 km by road (53 min by car)
- Cyber City 59 min · Airport 46 min by car at 9:30 am
- Within 3 km: 1 hospital, 1 school, 0 malls
The builder: Srv Automotives
- 1 project registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 11 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | LANDMARK THE HOMES 81 |
|---|---|
| Builder (promoter) | SRV AUTOMOTIVES PVT. LTD. |
| Location | SECTOR 81, GURUGRAM |
| RERA project ID | RERA-GRG-844-2021 |
| Registration certificate number | GGM/468/200/2021/36 DATED 16.07.2021 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 28/02/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.0 acres |
| Licence | 04 of 2021 (02-03-2021) |
| Estimated cost of the project | ₹16,733.1 lakh (₹167.33 crore) |
| Total units (plots, apartments, shops) | 780 |
| Unit sizes (carpet area, as declared) | 12 units of 76 sq ft carpet; 7 units of 79 sq ft carpet (3 towers); 36 units of 194 sq ft carpet (3 towers); 2 units of 280 sq ft carpet (3 towers); 1 unit of 335 sq ft carpet (3 towers); 45 units of 348 sq ft carpet (8 towers); 2 units of 396 sq ft carpet (3 towers); 9 units of 399 sq ft carpet (8 towers); 2 units of 402 sq ft carpet (3 towers); 6 units of 414 sq ft carpet (3 towers); 10 units of 451 sq ft carpet (3 towers); 1 unit of 538 sq ft carpet (3 towers); 112 units of 560 sq ft carpet (8 towers); 80 units of 567 sq ft carpet (8 towers); 1 unit of 581 sq ft carpet (3 towers); 2 units of 611 sq ft carpet (3 towers); 448 units of 645 sq ft carpet; 1 unit of 783 sq ft carpet (3 towers); 1 unit of 796 sq ft carpet (3 towers); 1 unit of 995 sq ft carpet (3 towers); 1 unit of 1,051 sq ft carpet (3 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 02-06-2021 |
| Building plans approved on | 02-06-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-12-2021 |
|---|---|
| Likely completion date | 28-02-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
| Latest report submitted on | 16-Mar-2026 |
| Quarterly reports listed on the portal | 17 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹234.75 lakh (₹2.35 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹-536.45 lakh (₹-5.36 crore) |
| Put in by the builder in the quarter | ₹1,916.61 lakh (₹19.17 crore) |
| Spent on construction of apartments in the quarter | ₹773.7 lakh (₹7.74 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹844.86 lakh (₹8.45 crore) |
| Project bank account (escrow): deposited in the quarter | ₹167.71 lakh (₹1.68 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹168.63 lakh (₹1.69 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 694 apartments |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹911.41 lakh (₹9.11 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 06 Jan 2026, for 31 Dec 2025 |
|---|---|
| Overall work complete | 97.5% |
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in