Laxmi Apartments

Pareena Infrastructure · Sector 99, Gurugram

Registered with RERA: Jul 2017

Is it legal?

Will it be delivered on time?

Location

Location shown for Sector 99; the exact site was not found.

The builder: Pareena Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameLAXMI APARTMENTS
Builder (promoter)PAREENA INFRASTRUCTURE PVT. LTD.
LocationVILLAGE GOPAL PUR, SECTOR-99, GURUGRAM
RERA project IDRERA-GRG-556-2020
Registration certificate number25 OF 2017 DATED 27.07.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to14/09/2020
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5 acres
Licence106 of 2014 dated 14-08-2014
Estimated cost of the project₹13,556 lakh (₹135.56 crore)
Total units (plots, apartments, shops)837
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered800
Units unsold when registered37
Layout plan approved on09-12-2016
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date14-09-2020
Revised completion date14-09-2020
Infrastructure: projected completion31-05-2020
Infrastructure: percentage complete when registered90%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2021 (JAN-MAR)
Latest report submitted on30-May-2025
Quarterly reports listed on the portal10

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2021 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1 lakh (₹0.01 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹45.08 lakh (₹0.45 crore)
Project bank account (escrow): withdrawn in the quarter₹44.4 lakh (₹0.44 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)Not found in the records checked
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 25-07-2014
  • Zoning Plan: Obtained Approval 14-08-2014
  • Service Plans: Obtained Approval 11-06-2021
  • Electricity Plans: Obtained Approval 05-10-2020
  • Fire NOC: Obtained Approval 16-09-2015

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 17 Apr 2021, for 31 Mar 2021
By part
  • Sub structure: 93%, Excavation done, raft foundation laid, two basements, basement waterproofing done
  • Super structure: 90%, Stilt floor done, walls on floors, staircase, lift wells and lift lobbies in progress
  • MEP - Mechanical (lifts, ventilation): 100%, Internal mechanical works completed
  • MEP - Electrical (conduiting, wiring, fixtures): 80%, Internal electrical works including wiring in progress
  • MEP - Plumbing and firefighting (piping, pumps, fixtures): 80%, Internal plumbing works to be started
  • Finishing - Internal (plaster, tiling, flooring, painting): 55%, Wall plastering, tiling and flooring in progress; white washing to be started
  • Finishing - External (plaster, painting, facade): 80%, External plaster in progress
  • Internal roads and pavements: 93%, In progress
  • Parking (covered): 95%, In progress
  • Parking (open): 0%
  • Water supply: 95%, In progress
  • Sewerage (chamber, lines, septic tanks, STP): 95%, In progress
  • Storm water drains: 95%, In progress
  • Landscaping and tree plantation: 90%, To be started
  • Parks and playgrounds: 90%, To be started
  • Shopping area: 25%, To be started
  • Street lighting and electrification: 93%, In progress
  • Treatment and disposal of sewage and sullage water (STP): 95%, In progress
  • Water conservation, rain water harvesting: 90%, To be started
  • Fire protection and fire safety requirements: 95%, In progress
  • Electrical meter room, sub-station, receiving station: 95%, In progress
  • Community Centre: 95%, In progress
Unclear in the certificate
  • Table A has a blank building/tower number, so the figures are not tied to a named tower or block.
  • The slab count entry '804/804' and the floor entry '(10, 11, 12 floors)' are unclear as to which tower they refer to.
  • The certificate gives no single overall percentage of construction complete or of work done in the quarter.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project45
Cases
Decided cases against PAREENA INFRASTRUCTURE PVT. LTD. (all its projects)187 (Complaint: 120; Execution of an earlier order: 21; Compensation: 46)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026