Projects · LION INFRADEVELOPERS LLP

Lid Nivasa

Lion Infradevelopers · Sector 6, Gurugram

Registered with RERA: Dec 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 6; the exact site was not found.

The builder: Lion Infradevelopers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameLID NIVASA
Builder (promoter)LION INFRADEVELOPERS LLP
LocationGREEN VALLEY - 2, SECTOR-6, S OHNA
RERA project IDRERA-GRG-2095-2025
Registration certificate numberGGM/1020/752/2025/123 DATED 10.12.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/09/2030
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.2213 acres
Licence188 OF 2023 dated 15-09-2023
Estimated cost of the project₹12,707.46 lakh (₹127.07 crore)
Total units (plots, apartments, shops)160
Unit sizes (carpet area, as declared)160 units averaging about 740 sq ft carpet (40 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on28-08-2025
Building plans approved on28-08-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-11-2025
Likely completion date30-09-2030

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal3

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹412.03 lakh (₹4.12 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹3.76 lakh (₹0.04 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹222.54 lakh (₹2.23 crore)
Project bank account (escrow): deposited in the quarter₹288.42 lakh (₹2.88 crore)
Project bank account (escrow): withdrawn in the quarter₹134.87 lakh (₹1.35 crore)
Project bank account (escrow): balance at quarter end₹606.61 lakh (₹6.07 crore)
Units in the project (apartments / plots)160 apartments
Sold in the quarter6 apartments
EDC (development charges): paid / due as on date₹46.13 lakh (₹0.46 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 08-12-2023
  • Zoning Plan: Obtained Approval 08-12-2023
  • Electricity Plans: Obtained Approval 03-11-2023
  • Building Plans: Obtained Approval 25-08-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 09 Oct 2026, for 30 Sep 2026
By part
  • All 40 Plots: 1%, Excavation in process; sub structure work done Rs 16.52 lakhs cumulative, Rs 3.76 lakhs in the quarter. Superstructure, MEP and finishing not yet started.
Unclear in the certificate
  • No single overall percentage of construction completed is stated; Table A gives percentages only for each component.
  • Table A covers all 40 plots together; no separate tower-wise figures are given.
  • Table B lists common areas and amenities as not proposed, with no work done.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against LION INFRADEVELOPERS LLP (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in