Projects · LEKH BUILDTECH PRIVATE LIMITED
M3M 113 Market
Lekh Buildtech · Sector 113, Gurugram
Is it legal?
- RERA registered, valid till Apr 2023 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not apply to extend registration, submit completion/occupation certificate, or requisite documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
Will it be delivered on time?
- Original deadline Oct 2021, extended to Apr 2023
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jan–Mar 2023):
- Done: 11 parts
- 0% of the work is still to be done by cost (CA certificate, Mar 2023)
What's on offer?
- 105 units: 102 sold, 3 unsold (builder's certificate, Mar 2023)
- Registration now covers 105 units
- 105 plots, 58–437 sq yd
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 5 km by road (9 min by car)
- Cyber City 47 min · Airport 27 min by car at 9:30 am
- Within 3 km: 5 hospitals, 2 schools, 1 mall
The builder: Lekh Buildtech
- 3 projects registered in Gurugram
- 2 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M 113 MARKET |
|---|---|
| Builder (promoter) | LEKH BUILDTECH PRIVATE LIMITED |
| Location | SECTOR-113, GURUGRAM MANESAR URBAN COMPLEX, GURUGRAM, HARYANA |
| RERA project ID | RERA-GRG-319-2019 |
| Registration certificate number | GGM/365/97/2019/59 DATED- 15.10.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/04/2023 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 8.526 acres |
| Licence | 123 of 2019 dated 17.09.2019 |
| Estimated cost of the project | ₹14,775.56 lakh (₹147.76 crore) |
| Total units (plots, apartments, shops) | 105 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 17-09-2019 |
| Building plans approved on | 17-09-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-10-2019 |
|---|---|
| Likely completion date | 31-10-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2023 (JAN-MAR) |
| Latest report submitted on | 18-Apr-2023 |
| Quarterly reports listed on the portal | 13 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2023 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹138.51 lakh (₹1.39 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹86.26 lakh (₹0.86 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹14.84 lakh (₹0.15 crore) |
| Project bank account (escrow): deposited in the quarter | ₹138.51 lakh (₹1.39 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹810.36 lakh (₹8.1 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 105 plots |
| Sold in the quarter | 0 plots |
| EDC (development charges): paid / due as on date | ₹4,580.34 lakh (₹45.8 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Mar 2023, for JAN – MAR 2023 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against LEKH BUILDTECH PRIVATE LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in