Projects · LOON LAND DEVELOPMENT LIMITED
M3M Antalya Hills Phase II
Loon Land Development · Sector 79, Gurugram
Registered with RERA: Jan 2023
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jun 2026)
- HRERA opened a case of its own against the builder in Aug 2023 (still open):
- Why: did not submit approved service plans and estimates within 3 months of registration
- Latest: 15 Dec 2023: clubbed with supersession matter; next hearing 01 Jan 2024
- At stake: show-cause asks why registration should not be revoked; no penalty imposed
Will it be delivered on time?
- Deadline Jun 2026, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2024):
- In progress: Sub structure 75%, Super structure 50%, Electrical 30%, Mechanical 0%, Plumbing and firefighting 0%, Internal finishing 0%, and 1 more
- Money: ₹547.9 crore spent of ₹1,330.8 crore; ₹782.9 crore still to spend (CA certificate, Sep 2024)
What's on offer?
- 1,392 units: 1,384 sold, 8 unsold (builder's certificate)
- Sizes declared at registration (2,068 units):
- 420 units averaging about 630 sq ft carpet (105 towers)
- 336 units averaging about 650 sq ft carpet (84 towers)
- 196 units averaging about 670 sq ft carpet (49 towers)
- 732 units averaging about 860 sq ft carpet (183 towers)
- 124 units averaging about 930 sq ft carpet (31 towers)
- 72 units averaging about 940 sq ft carpet (18 towers)
- 7 less common sizes: see the full list below
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Sector 55–56, 17.4 km by road (52 min by car)
- Cyber City 60 min · Airport 50 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: Loon Land Development
- 10 projects registered in Gurugram, 4 lapsed
- 0 with an occupation certificate on record
- 20 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M ANTALYA HILLS PHASE II |
|---|---|
| Builder (promoter) | LOON LAND DEVELOPMENT LIMITED |
| Location | SECTOR 79, GURUGRAM |
| RERA project ID | RERA-GRG-1248-2022 |
| Registration certificate number | GGM/662/394/2023/06 DATED 12.01.2023 (SUPERSEDED BY GGM/833/565/2024/60 DATED 03.06.2024) |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/06/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 15.5299 acres |
| Licence | 195 of 2022 dated 29.11.2022 |
| Estimated cost of the project | ₹1,33,083.41 lakh (₹1,330.83 crore) |
| Total units (plots, apartments, shops) | 2068 |
| Unit sizes (carpet area, as declared) | 420 units averaging about 630 sq ft carpet (105 towers); 336 units averaging about 650 sq ft carpet (84 towers); 196 units averaging about 670 sq ft carpet (49 towers); 24 units averaging about 780 sq ft carpet (6 towers); 48 units averaging about 830 sq ft carpet (12 towers); 732 units averaging about 860 sq ft carpet (183 towers); 28 units averaging about 890 sq ft carpet (7 towers); 124 units averaging about 930 sq ft carpet (31 towers); 72 units averaging about 940 sq ft carpet (18 towers); 68 units averaging about 970 sq ft carpet (17 towers); 4 units of 2,782 sq ft carpet (1 tower); 8 units of 5,997 sq ft carpet (2 towers); 8 units of 6,258 sq ft carpet (2 towers) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 29-11-2022 |
| Building plans approved on | 26-12-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2023 |
|---|---|
| Likely completion date | 30-06-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2024 (JUL-SEP) |
| Latest report submitted on | 30-Oct-2024 |
| Quarterly reports listed on the portal | 6 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2024 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹6,699.43 lakh (₹66.99 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹5,950.12 lakh (₹59.5 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹911.69 lakh (₹9.12 crore) |
| Project bank account (escrow): deposited in the quarter | ₹6,699.43 lakh (₹66.99 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹3,652 lakh (₹36.52 crore) |
| Project bank account (escrow): balance at quarter end | ₹3,225.33 lakh (₹32.25 crore) |
| Units in the project (apartments / plots) | 1392 apartments |
| Sold in the quarter | 20 apartments |
| EDC (development charges): paid / due as on date | ₹832.19 lakh (₹8.32 crore) paid; ₹832.19 lakh (₹8.32 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 03 Oct 2024, for July to September 2024 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against LOON LAND DEVELOPMENT LIMITED (all its projects) | 20 (Complaint: 19; Compensation: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in