Projects · HANS PROPCON PVT. LTD., GLORY INFRACON PVT. LTD., BLOSSOM PROPBUILD PVT. LTD.
M3M FLORA68
Hans Propcon · Sector 68, Gurugram
Registered with RERA: Jul 2022
Is it legal?
- RERA registered, valid till Jul 2024 (date has passed)
- HRERA opened a case of its own against the builder in Aug 2025 (still open):
- Why: did not complete the project within the time it declared
- Latest: order uploaded 19 Sep 2025; next hearing 01 Oct 2025
Will it be delivered on time?
- Deadline Jun 2026, never extended (date has passed)
- Occupation certificate (Oct 2023) covers: Tower-13, Basement-T-2 and two nursery schools (114 flats)
- Construction, as certified by the architect (Jul–Sep 2023):
- Done: Group housing tower - sub structure, Group housing tower - super structure, Group housing tower - mechanical mep, Group housing tower - electrical mep, Group housing tower - external finishing
- In progress: Group housing tower - plumbing and firefighting 95%, Group housing tower - internal finishing 95%, Group housing tower - waterproofing of sub-structure 90%, Fire protection and fire safety requirements 85%, Internal roads and pavements 65%, Water supply 65%, and 15 more
- Money: ₹55.7 crore spent of ₹52.7 crore (CA certificate, Sep 2023)
What's on offer?
- 114 units: 102 sold, 12 unsold (builder's certificate, Sep 2023)
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 3 BHK
- 114 units, as declared to HRERA:
- 114 units averaging about 830 sq ft carpet (1 tower)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units.
Location
- Nearest metro: Sector 55–56, 10.4 km by road (42 min by car)
- Cyber City 61 min · Airport 59 min by car at 9:30 am
- Within 3 km: 8 hospitals, 4 schools, 2 malls
The builder: Hans Propcon
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M FLORA68 |
|---|---|
| Builder (promoter) | HANS PROPCON PVT. LTD., GLORY INFRACON PVT. LTD., BLOSSOM PROPBUILD PVT. LTD. |
| Location | SECTOR -68, GURUGRAM |
| RERA project ID | RERA-GRG-878-2021 |
| Registration certificate number | GGM/594/326/2022/69 DATED 18.07.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/07/2024 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 0.905 acres |
| Licence | 93 of 2014 dated 13.08.2014 |
| Estimated cost of the project | ₹5,270.73 lakh (₹52.71 crore) |
| Total units (plots, apartments, shops) | 114 |
| Unit sizes (carpet area, as declared) | 114 units averaging about 830 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | 2 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 06-07-2021 |
| Building plans approved on | 06-07-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 24-06-2021 |
|---|---|
| Likely completion date | 30-06-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2023 (JUL-SEP) |
| Latest report submitted on | 05-Aug-2024 |
| Quarterly reports listed on the portal | 4 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2023 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹1,247.63 lakh (₹12.48 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹229.78 lakh (₹2.3 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹517.92 lakh (₹5.18 crore) |
| Project bank account (escrow): deposited in the quarter | ₹1,247.63 lakh (₹12.48 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹3,000 lakh (₹30 crore) |
| Project bank account (escrow): balance at quarter end | ₹435.72 lakh (₹4.36 crore) |
| Units in the project (apartments / plots) | 114 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹122.64 lakh (₹1.23 crore) paid; ₹122.64 lakh (₹1.23 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 03 Oct 2023, for JULY to SEP 2023 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against HANS PROPCON PVT. LTD., GLORY INFRACON PVT. LTD., BLOSSOM PROPBUILD PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in