Projects · MANGLAM MULTIPLEX PVT. LTD AND OTHERS
M3M Latitude ( Tower R-01)
Manglam Multiplex Pvt. Ltd And Others · Sector 65, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Jan 2023 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit a quarterly progress report (May 2022, open)
- Allegedly let project registration certificate expire; completion certificate not yet obtained (Jul 2024, open)
- Did not file REP-I project updates, hard copy documents and quarterly progress reports (Nov 2019, open). At stake: Rs 25,000 daily penalty from 31 Dec 2019; capped at 5% of project cost
- 2 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 refund ordered)
Will it be delivered on time?
- Deadline Jan 2023, never extended (date has passed)
- Occupation certificate (Jan 2021) covers: Tower R-01 only, 160 dwelling units (160 flats)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 3 BHK + servant room: 160 units
Location
- Nearest metro: Sector 55–56, 7 km by road (22 min by car)
- Cyber City 48 min · Airport 57 min by car at 9:30 am
- Within 3 km: 12 hospitals, 21 schools, 6 malls
The builder: Manglam Multiplex Pvt. Ltd And Others
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 4 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M LATITUDE ( TOWER R-01) |
|---|---|
| Builder (promoter) | MANGLAM MULTIPLEX PVT. LTD AND OTHERS |
| Location | SECTOR-65, GURUGRAM, HARYANA |
| RERA project ID | RERA-GRG-602-2020 |
| Registration certificate number | 56 OF 2017 DATED 17.8.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/01/2023 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 1.2125 acres |
| Licence | 234 of 2007 dated 16.10.2007 (54.61225 Acres) , 52 dated.28.08.2009 (0.4375 Acres) , 35 dated 6.05.2010 (1 Acre) |
| Estimated cost of the project | ₹42,684.62 lakh (₹426.85 crore) |
| Total units (plots, apartments, shops) | 160 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 3 BHK + servant room: 160 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 109 |
| Units unsold when registered | 51 |
| Layout plan approved on | 01-04-2016 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-01-2023 |
|---|---|
| Revised completion date | 31-01-2023 |
| Infrastructure: projected completion | 31-01-2023 |
| Infrastructure: percentage complete when registered | 25.29% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against MANGLAM MULTIPLEX PVT. LTD AND OTHERS (all its projects) | 4 (Complaint: 3; Compensation: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in