Projects · UNION BUILDMART PRIVATE LIMITED
M3M Mansion
Union Buildmart · Sector 113, Gurugram
Registered with RERA: Mar 2024
Is it legal?
- RERA registered, valid till Mar 2030
- HRERA opened a case of its own against the builder in Aug 2024 (still open)
Will it be delivered on time?
- Deadline Feb 2032, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: Raft foundation, Pile foundation
- In progress: Excavation 90%, Basement level 2 85%, Basement level 1 83%, Stilt floor / ground floor 79%, Sub structure 71%, Super structure 47%, and 17 more
- Money: ₹1,324.6 crore spent of ₹2,333 crore; ₹1,008.4 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 968 units: 823 sold, 145 unsold (builder's certificate)
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 3 BHK
- 3 BHK + study + utility
- 3.5 BHK
- 4 BHK + study + utility
- 4.5 BHK
- 968 units, as declared to HRERA:
- 961 units averaging about 1,420 sq ft carpet (8 towers)
- 7 units of 1,825 sq ft carpet
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units.
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 4.1 km by road (6 min by car)
- Cyber City 45 min · Airport 24 min by car at 9:30 am
- Within 3 km: 5 hospitals, 2 schools, 1 mall
The builder: Union Buildmart
- 6 projects registered in Gurugram
- 3 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M MANSION |
|---|---|
| Builder (promoter) | UNION BUILDMART PRIVATE LIMITED |
| Location | VILLAGE CHAUMA,SECTOR 113,GUR UGRAM |
| RERA project ID | RERA-GRG-1547-2024 |
| Registration certificate number | GGM/802/534/2024/29 DATED 18.03.2024 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/03/2030 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 8.710 acres |
| Licence | 229 of 2023(02-11-2023) |
| Estimated cost of the project | ₹2,33,297.9 lakh (₹2,332.98 crore) |
| Total units (plots, apartments, shops) | 968 |
| Unit sizes (carpet area, as declared) | 961 units averaging about 1,420 sq ft carpet (8 towers); 7 units of 1,825 sq ft carpet |
| Flat types (BHK), as stated by the builder | 3 BHK; 3 BHK + study + utility; 3.5 BHK; 4 BHK + study + utility; 4.5 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 20-02-2024 |
| Building plans approved on | 20-02-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-03-2024 |
|---|---|
| Likely completion date | 29-02-2032 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 15-Oct-2026 |
| Quarterly reports listed on the portal | 10 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹9,829.74 lakh (₹98.3 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹4,325.9 lakh (₹43.26 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹3,657 lakh (₹36.57 crore) |
| Project bank account (escrow): deposited in the quarter | ₹9,829.74 lakh (₹98.3 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹9,500 lakh (₹95 crore) |
| Project bank account (escrow): balance at quarter end | ₹664.88 lakh (₹6.65 crore) |
| Units in the project (apartments / plots) | 968 apartments |
| Sold in the quarter | 6 apartments |
| EDC (development charges): paid / due as on date | ₹4,776.74 lakh (₹47.77 crore) paid; ₹4,776.74 lakh (₹47.77 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 01 Oct 2026, for July to September 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against UNION BUILDMART PRIVATE LIMITED (all its projects) | 5 (Complaint: 5) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in