M3M MARINA/M3M Sierra 68 ( Group Housing Colony)
Hans Propcon · Sector 68, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Nov 2022 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit its quarterly progress report (May 2022, open)
- Allegedly let project registration certificate expire (Section 4(2) violation alleged) (open)
- Did not file online and hard-copy REP-I (Part A-H) project updates or quarterly progress reports (Nov 2019, open). At stake: Rs 25,000 per day while default continues; cumulative cap five percent of project cost
- 2 more cases: reply 4
- 2 complaints about this project decided by HRERA since Nov 2023 (2 refund ordered)
Will it be delivered on time?
- Deadline Jan 2022, never extended (date has passed)
- Occupation certificate (Sep 2020) covers: Towers 1 to 12, including EWS, shops and community building (1,069 flats)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK + study: 1,076 units
Location
- Nearest metro: Sector 55–56, 10 km by road (39 min by car)
- Cyber City 59 min · Airport 56 min by car at 9:30 am
- Within 3 km: 8 hospitals, 4 schools, 2 malls
The builder: Hans Propcon
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 19 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | M3M MARINA/M3M SIERRA 68 ( GROUP HOUSING COLONY) |
|---|---|
| Builder (promoter) | HANS PROPCON PVT. LTD |
| Location | SECTOR-68, GURUGRAM |
| RERA project ID | RERA-GRG-596-2020 |
| Registration certificate number | 57(A) OF 2017 DATED 17.8.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/11/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 13.2118 acres |
| Licence | 93 of 2014 dated 13.08.2014 |
| Estimated cost of the project | ₹63,916.51 lakh (₹639.17 crore) |
| Total units (plots, apartments, shops) | 1076 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK + study: 1,076 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 456 |
| Units unsold when registered | 444 |
| Layout plan approved on | 03-05-2016 |
| Building plans approved on | 03-05-2016 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-01-2022 |
|---|---|
| Revised completion date | 31-01-2022 |
| Infrastructure: projected completion | 31-01-2022 |
| Infrastructure: percentage complete when registered | 36% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 2 |
|---|---|
| Cases |
|
| Decided cases against HANS PROPCON PVT. LTD (all its projects) | 19 (Compensation: 6; Complaint: 13) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026